Aurelia Metals completed mine construction activities, and commenced commissioning of the processing facilities at Hera. On 12 September 2014 the Group achieved its first gold pour at Hera and during the period achieved pre-production gold, silver and concentrate sales of $9,768,615 (2013: nil) as a credit against development expenditure of $20,531,692 (2013: $39,869,520). Exploration expenditure for the half year ending
[...]