Paramount Gold and Silver Extends Mineralized Strike of New San Miguel Target to 1.5 Km
WINNEMUCCA, NEVADA -- (Marketwire) -- 11/28/12 -- Paramount Gold and Silver Corp. (NYSE MKT: PZG) (NYSE Amex: PZG) (TSX: PZG)(FRANKFURT: P6G)(WKN: A0HGKQ) ("Paramount") today reported results from four additional holes into the growing La Bavisa target on Paramount's 100%-owned San Miguel Project in Mexico.
The La Bavisa target, located 700 meters north of the high-grade Don Ese resource, has been traced on surface for over 2.8 km. To date, a total of eight drill holes have been completed into La Bavisa, defining a mineralized strike of 1.5 km. containing intercepts up to 12.20 meters wide grading 1.22 g/T gold and 255.8 g/T silver (approximately 5.5 g/T of gold equivalent at a conservative silver-to-gold ratio of 60:1). La Bavisa has not yet been incorporated into San Miguel's resource estimates and therefore is not part of the project's first Preliminary Economic Assessment scheduled for completion by year-end.
Paramount also reported promising results from the first holes drilled at another new target known as Barranca Blanca, also located in the Don Ese area immediately adjacent to the Don Ese resource to the southeast. Barranca Blanca has an on-surface strike length of at least 1.2 kilometers and appears to be similar to the other occurrences in the immediate area. The three preliminary holes were drilled to test the structure for precious metals, returning encouraging values of up to 0.7 g/T of gold and 31.2 g/T of silver. The Barranca Blanca will now be drilled in a more systematic fashion designed to intersect the optimum elevations for higher grade material.
Paramount CEO Christopher Crupi commented: "The Don Ese resource area has emerged as a major target, potentially the most important of the four main mineralized zones on San Miguel. A swarm of higher-grade structures has now been identified at Don Ese and are likely to be exploited together. The reality is that San Miguel continues to grow quickly and we are far from exhausting our list of excellent opportunities for resource expansion. Our challenge is to develop current engineering and economic projections while at the same time undergoing rapid resource expansion."
The latest drill results include:
--------------------------------------------------------------------------
Hole # Area Total
Length From To Width Au Ag
(m) (m) (m) (m) g/T g/T
--------------------------------------------------------------------------
BV-12-005 LA BAVISA 649.40 503.00 513.70 10.70 0.780 148.96
including 503.00 506.85 3.85 1.650 300.42
517.35 528.25 10.90 0.230 32.68
543.75 545.95 2.20 0.740 53.91
--------------------------------------------------------------------------
BV-12-006 LA BAVISA 643.30 440.65 445.00 4.35 0.130 27.18
450.25 455.00 4.75 0.080 13.05
470.80 471.45 0.65 0.544 163.00
633.95 638.35 4.40 0.200 5.56
--------------------------------------------------------------------------
BV-12-007 LA BAVISA 579.30 502.50 518.30 15.80 0.620 89.74
including 507.90 514.00 6.10 1.400 189.61
--------------------------------------------------------------------------
BV-12-008 LA BAVISA 673.85 529.05 530.35 1.30 1.130 175.51
563.00 565.35 2.35 0.250 41.22
597.50 598.25 0.75 0.937 116.00
605.50 616.35 10.85 0.220 29.50
including 607.60 609.00 1.40 0.420 68.04
including 611.90 613.95 2.05 0.580 68.92
628.30 629.50 1.20 2.700 17.30
632.70 636.25 3.55 2.450 220.78
637.25 640.20 2.95 0.200 17.81
--------------------------------------------------------------------------
BB-12-001 BARRANCA
BLANCA 432.85 250.15 252.65 2.50 0.150 25.87
--------------------------------------------------------------------------
BB-12-002 BARRANCA
BLANCA 371.85 309.50 312.70 3.20 0.220 31.22
--------------------------------------------------------------------------
BB-12-003 BARRANCA 463.45 241.15 250.90 9.75 0.350 10.43
BLANCA including 246.80 249.10 2.30 0.710 13.52
271.20 273.00 1.80 0.140 10.51
275.70 278.80 3.10 0.120 10.31
--------------------------------------------------------------------------
These holes were drilled to intersect the structure at right angles; however deeper holes may have intersected the structure at lower angles. True widths are expected to be at least 80% of reported intercepts.
NI 43-101 Disclosure
Exploration activities at San Miguel are being conducted by Paramount Gold de Mexico S.A de C.V personnel under the supervision of Glen van Treek, Exploration Vice President of the Company and Bill Threlkeld, a Qualified Person as defined by National Instrument 43-101, who have both reviewed and approved this press release. An ongoing quality control/quality assurance protocol is being employed for the program including blank, duplicate and reference standards in every batch of assays. Cross-check analyses are being conducted at a second external laboratory on 10% of the samples. Samples are being assayed at ALS Chemex, Vancouver, B.C., using fire assay atomic absorption methods for gold and aqua regia digestion ICP methods for other elements.
About Paramount Gold
Paramount is a U.S.-based exploration and development company with multi-million ounce advanced stage precious metals projects in Nevada (Sleeper) and northern Mexico (San Miguel). Fully-funded exploration and engineering programs are now in progress at these two core projects which are expected to generate substantial additional value for our shareholders.
The Sleeper Gold Project is located off a main highway about 25 miles from the town of Winnemucca. In 2010, Paramount acquired a 100% interest in the project including the original Sleeper high-grade open pit mine operated by Amax Gold from 1986 to 1996 as well as staked and purchased lands now totaling 2,570 claims and covering about 47,500 acres which stretch south down trend to Newmont's Sandman project. This acquisition is consistent with the Company's strategy of district-scale exploration near infrastructure in established mining camps.
The San Miguel Project consists of over 142,000 hectares (over 353,000 acres) in the Palmarejo District of northwest Mexico, making Paramount the largest claim holder in this rapidly growing precious metals mining camp. The San Miguel Project is ideally situated near established, low cost production where the infrastructure already exists for early, cost-effective exploitation. A PEA for San Miguel is now in progress.
SUMMARY OF PZG'S ESTIMATED NI 43-101 COMPLIANT RESOURCES
MEASURED AND INDICATED RESOURCES
----------------------------------------------------------------------------
PROJECT Tonnes Au g/T Au Ounces Ag g/T Ag Ounces
----------------------------------------------------------------------------
San Miguel 23,918,000 0.83 639,000 70.0 53,559,000
----------------------------------------------------------------------------
Sleeper 326,963,000 0.33 3,479,000 3.86 40,606,000
----------------------------------------------------------------------------
Total 4,118,000 94,165,000
----------------------------------------------------------------------------
INFERRED RESOURCES
----------------------------------------------------------------------------
PROJECT Tonnes Au g/T Au Ounces Ag g/T Ag Ounces
----------------------------------------------------------------------------
San Miguel 37,470,000 0.69 830,000 38.00 46,243,000
----------------------------------------------------------------------------
Sleeper 223,624,000 0.27 1,972,000 2.84 20,450,000
----------------------------------------------------------------------------
Total 2,802,000 60,693,000
----------------------------------------------------------------------------
Cautionary Note to U.S. Investors Concerning Estimates of Indicated and Inferred Resources
This news release uses the terms "measured and indicated resources" and "inferred resources". We advise U.S. investors that while these terms are defined in, and permitted by, Canadian regulations, these terms are not defined terms under SEC Industry Guide 7 and not normally permitted to be used in reports and registration statements filed with the SEC. "Inferred resources" have a great amount of uncertainty as to their existence, and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an inferred mineral resource will ever be upgraded to a higher category. Under Canadian rules, estimates of inferred mineral resources may not form the basis of a feasibility study or prefeasibility studies, except in rare cases. The SEC normally only permits issuers to report mineralization that does not constitute SEC Industry Guide 7 compliant "reserves", as in-place tonnage and grade without reference to unit measures. U.S. investors are cautioned not to assume that any part or all of mineral deposits in this category will ever be converted into reserves. U.S. investors are cautioned not to assume that any part or all of an inferred resource exists or is economically or legally minable.
Safe Harbor for Forward-Looking Statements:
This release and related documents may include "forward-looking statements" including, but not limited to, statements related to the interpretation of drilling results and potential mineralization, future exploration work at the San Miguel Project and the expected results of this work, estimates of resources including expected volumes and grades and the anticipated completion of a PEA. Forward-looking statements are statements that are not historical fact and are subject to a variety of risks and uncertainties which could cause actual events to differ materially from those reflected in the forward-looking statements including fluctuations in the price of gold, inability to complete drill programs on time and on budget, and future financing ability. Paramount's future expectations, beliefs, goals, plans or prospects constitute forward-looking statements within the meaning of the United States Private Securities Litigation Reform Act of 1995 and other applicable securities laws. Words such as "believes," "plans," "anticipates," "expects," "estimates" and similar expressions should also be considered to be forward-looking statements. There are a number of important factors that could cause actual results or events to differ materially from those indicated by such forward-looking statements, including, but not limited to: uncertainties involving interpretation of drilling results, environmental matters, lack of ability to obtain required permitting, equipment breakdown or disruptions, and the other factors described in Paramount's Annual Report on Form 10-K for the year ended June 30, 2012 and its most recent quarterly reports filed with the SEC.
Except as required by applicable law, Paramount disclaims any intention or obligation to update any forward-looking statements as a result of developments occurring after the date of this document.
Contacts:
Paramount Gold and Silver Corp.
Glen Van Treek, VP Exploration
Chris Theodossiou, Investor Relations
866-481-2233