• Freitag, 15 November 2024
  • 15:40 Uhr Frankfurt
  • 14:40 Uhr London
  • 09:40 Uhr New York
  • 09:40 Uhr Toronto
  • 06:40 Uhr Vancouver
  • 01:40 Uhr Sydney

Moneta Announces Positive Preliminary Economic Assessment on Golden Highway Project with 24.4% Irr and $748M Npv

01.11.2012  |  CNW

TIMMINS, ON, Nov. 1, 2012 /CNW/ - Moneta Porcupine Mines Inc. (TSX: ME) (OTC: MPUCF) (XETRA: MOP) ("Moneta") announces results from a National Instrument 43-101 Preliminary Economic Assessment ("PEA") on its 100% owned Golden Highway Project ("Property") located east of Timmins, Ontario (Canada).

The results of the PEA demonstrate the potential technical and economic viability of establishing a new gold mine and mill complex on the Property. All currency amounts in this press release are expressed in Canadian dollars ($) unless otherwise noted.

PEA Economics (using US$1,350/oz gold - see sensitivity Table 1 below):

  • Pre-tax Net Present Value of $748 million (5% discount rate), 24.4% internal rate of return, 4.1 year payback period.

TABLE 1: ECONOMIC SENSITIVITY TO GOLD PRICE
Gold Price (US$)  BASE CASE:
$1,350
   $1,400   $1,500   $1,600   $1,700
Net Present Value ($ millions)7488581,0801,3011,523
Internal Rate of Return (%)24.426.831.335.539.5
Payback period4.13.73.32.92.6

 

Ian C. Peres, President and CEO of Moneta commented, "This Preliminary Economic Assessment demonstrates robust economics under the conservative US$1,350/oz gold base case scenario.  With a positive view on gold, the Golden Highway asset becomes increasingly attractive. We are particularly pleased to see a robust 88% potentially economic portion of the resource based on our recent Oct 2012 NI 43-101 resource estimate. Our exploration focus continues with drilling the large untested areas within the conceptual pits as well as other adjacent and high priority targets on the Property."

PEA Highlights:

  • Life of mine metal production of 3.8 million ounces gold with 92% recovery;
  • Pre-production capital costs of $607 million.
  • Processing facility throughput of 25,000 tonnes per day ("tpd");
  • Life of mine average cash costs of $794 per ounce gold;
  • Average diluted mill head grade of 1.11 g/t gold;
  • Average annual production of 288,000 gold ounces;
  • Operating strip ratio of 5.6 : 1;
  • 12 year mine life

Areas of upside potential include:

  • Four additional gold zones on the property outside NI 43-101 resource;
  • Undrilled areas within the conceptual pits;
  • Potential below current constrained pits - similar to Southwest Zone;
  • Exploration potential within 12km of strike of the Property.

The PEA incorporates the recent National Instrument 43-101 ("NI 43-101") mineral resource estimate of  31.1 Mt at 1.09 g/t Au indicated plus 83.3 Mt at 1.20 g/t Au inferred (press release October 25, 2012). This PEA assumes that both open pit and underground mining methods would be used for resource extraction. Potentially economic open pit portions of the resources have been calculated assuming a dilution of 6% and a material loss of 2%. Potentially economic underground portions of the resources have been calculated assuming a dilution of 15% and a material loss of 10%.  With an open pit cut-off grade of 0.40 g/t gold, and an underground cut-off grade of 2.00 g/t gold, the resulting tonnages and grades for the open pit and underground conceptual mine plans are shown in Table 2:

TABLE 2: POTENTIALLY ECONOMIC PORTION OF IN PIT AND UNDERGROUND RESOURCES (1), (2), (3)
MiningCutoff Grade (g/t)INDICATEDINFERRED
Tonnes Au (g/t) Au (oz)Tonnes Au (g/t) Au (oz)
 In Pit 0.4025,859,0001.05873,00056,909,0000.891,628,000
Out of Pit2.001,279,0003.15130,00011,510,0003.151,166,000
Combined  0.40 / 2.00 27,138,000 1.15   1,003,000 68,419,000 1.27   2,794,000

 

 (1) The potentially economic portion of the mineral resources in this press release were estimated using the Canadian Institute of Mining, Metallurgy and Petroleum (CIM), CIM Standards on Mineral Resources and Reserves, Definitions and Guidelines prepared by the CIM Standing Committee on Reserve Definitions and adopted by CIM Council.
 (2)Mineral resources are reported in relation to conceptual pit shells.  Mineral resources are not mineral reserves and do not have demonstrated economic viability. All figures are rounded to reflect the relative accuracy of the estimate. All composites have been capped where appropriate.
 (3)Potentially economic open pit portions of the mineral resources are undiluted and reported at a cut-off grade of 0.40 g/t gold; potentially economic underground portions of the mineral resources are undiluted and reported at a cut-off grade of 2.00 g/t gold. Optimized cut-off grades are based on a gold price of US$1,350 per ounce and a foreign exchange rate of US$1.00 = C$1.00. Metallurgical recoveries are 92%.

Mining
The PEA is based on a processing facility of 25,000 tpd of blended feed from open pit and underground operations.  The open pit is designed as a conventional surface mining operation producing at an average rate of 22,500 tpd.  The underground mining is designed as bulk tonnage mining operation producing at an average rate of 2,500 tpd.

Mining operations reaching a sustained total annual material movement of 75 million tonnes will be achieved with 45m3 diesel hydraulic excavators, 320 tonne haulage trucks and track mounted diesel powered drill rigs with up to 200mm diameter blastholes drilled on 10 metre height benches.

The open pit scenario includes development of a large Southwest Zone, Gap and Windjammer (South/Central/North) pit and smaller 55 Zone pit.  The underground portion is scheduled to be in full production by way of ramp in the second year of operations, accessing over 1.3 million ounces of bulk underground gold resources.  Development of a shaft is scheduled for year 2, to be funded from operating cash flow. 

Infrastructure

The Project significantly benefits from world-class infrastructure, services and available skilled labor in the Timmins Camp. The project site is located 25km east of Matheson and is accessible year-round from paved provincial Highway 101 and a network of gravel and sand logging roads.

The Golden Highway Project mill and mine site is ideally located and characterized by outcrop and shallow overburden to the immediate southeast of the main open pit.  Along the east and northeast perimeter of the open pits, esker ridges form natural containment dykes for at least two sides of a tailings management facility. These nearby eskers contain significant quantities of coarse gravel and small boulder material, ideal for road upgrades and infrastructure construction materials.

The labour force for the construction and operation of this project are anticipated to be drawn from Kirkland Lake, Timmins, Matheson and nearby Quebec communities. The labour pool in this area is highly experienced in both construction and mining operations, requiring less training than many other remote or non-mining locations.

Infrastructure is anticipated to include:

  • Plant site and haul roads;
  • Administration buildings and assay lab;
  • Mine maintenance garage, warehouse and fuel storage facilities;
  • Fresh water supply and sewage treatment;
  • Tailings pond;
  • Power supplied by a 10 km long transmission line connecting to the provincial grid;

Operating Costs
Total operating costs are summarized in Table 3, as follows:

TABLE 3: OPERATING COSTS
Operating costC$ / tonne
Open pit mining (mineralized rock) $ 1.67
Open pit mining (waste rock) $ 1.60
Open pit mining (overburden) $ 1.25
Underground mining (longhole with paste backfill) $ 32.45
Processing $ 10.34
General and Administrative  $ 0.75
Royalties (no encumberances) no royalties

 

Pre-Production Costs and Sustaining Capital
The breakdown of open pit and underground pre-production and sustaining capital costs is supplied in Tables 4 and 5.  Open pit pre-production capital costs include overburden stripping, to expose the bedrock material to be mined, as well as waste rock stripping.  Open pit sustaining capital costs are to be funded by operating cash flow and include certain ongoing overburden stripping to expose mineralized material as the pit expands.

TABLE 4 - PRE-PRODUCTION CAPITAL
OPEN PIT CAPITALC$ (millions) 
    Overburden stripping  $ 68.8
    Waste stripping 35.0
    Process Plant243.0
    Site and mine infrastructure15.8
    Mine equipment 45.4
    Contingency49.0
  Sub-total $ 457.0
UNDERGROUND CAPITAL C$ (millions) 
    Main access ramp development 23.6
    Shaft development69.0
    Pre-production development57.5
  Sub-total $ 150.1
Total $ 607.1

 

TABLE 5 - SUSTAINING CAPITAL
OPEN PIT CAPITALC$ (millions) 
      Overburden stripping $ 192.5
      Waste stripping 66.0
      Equipment Lease132.0
   Sub-total $ 390.5
UNDERGROUND CAPITAL C$ (millions) 
     Underground development $ 83.8
Total $ 474.3

 

This PEA is preliminary in nature as it includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves and there is no certainty that the PEA will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

The PEA was prepared under the supervision of Mr. Eugene J. Puritch, P. Eng., of P&E Mining Consultants Inc. ("P&E"), Independent Qualified Persons ("QP"), as defined by National Instrument 43-101. Mr. Puritch has reviewed and approved the contents of this news release. A NI 43-101 compliant PEA Technical Report is currently being prepared by P&E and will be filed on SEDAR within 45 days of this news release.

About Moneta
Moneta holds a 100% interest in 5 core gold projects strategically located along the Destor Porcupine Fault Zone in the world class Timmins Camp with over 85 million ounces of past gold production.  Moneta's land position is one of the largest after three gold producers including the highly prospective Golden Highway Project which covers 12 kilometers of a volcanic/sedimentary belt along the Destor Porcupine Fault Zone and hosts a NI 43-101 resource estimate of 1,091,000 ounces indicated (31.1 Mt at 1.09 g/t Au) plus 3,204,000 ounces inferred (83.3 Mt at 1.20 g/t Au), clustered within 4 kilometres. The Golden Highway Project hosts exceptional infrastructure including paved highway access, water, electricity, skilled labor force and nearby mills.

Moneta's public documents may be accessed at www.sedar.com.  For further information on Moneta, please visit our website at www.monetaporcupine.com or email us at info@monetaporcupine.com.

This news release contains "forward-looking information" as defined in applicable securities laws (referred to herein as "forward-looking statements"). Forward looking statements include, but are not limited to, statements with respect to the cost and timing of the exploration of the Golden Highway Project, the other economic parameters of the project, as set out in its preliminary economic assessment; the success and continuation of exploration activities; estimates of mineral resources; acquisitions of additional mineral properties; the future price of gold; government regulations and permitting timelines; estimates of reclamation obligations that may be assumed; requirements for additional capital; environmental risks; and general business and economic conditions. Often, but not always, forward-looking statements can be identified by the use of words such as "plans", "expects", "is expected", "budget", "scheduled", "estimates", "continues", "forecasts", "projects", "predicts", "intends", "anticipates" or "believes", or variations of, or the negatives of, such words and phrases, or statements that certain actions, events or results "may", "could", "would", "should", "might" or "will" be taken, occur or be achieved. Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the Company's actual results, performance or achievements to be materially different from any of its future results, performance or achievements expressed or implied by forward-looking statements. These risks, uncertainties and other factors include, but are not limited to, the assumptions underlying the preliminary economic assessment not being realized, decrease of future gold prices, cost of labour, supplies, fuel and equipment rising, changes in equity markets, actual results of current exploration, changes in project parameters, exchange rate fluctuations, delays and costs inherent to consulting and accommodating rights of First Nations, title risks, regulatory risks and uncertainties with respect to obtaining necessary surface rights and permits or delays in obtaining same, and other risks involved in the gold exploration and development industry, as well as those risk factors discussed in the section entitled " Description of Business-Risk Factors in Moneta's 2011 Annual Information Form and its other SEDAR filings from time to time. Forward-looking statements are based on a number of assumptions which may prove to be incorrect, including, but not limited to, the availability of financing for the Company's exploration and development activities; the timelines for the Company's exploration activities on the Golden Highway Project; the availability of certain consumables and services; assumptions made in mineral resource estimates, including geological interpretation grade, recovery rates, and operational costs; and general business and economic conditions. All forward-looking statements herein are qualified by this cautionary statement. Accordingly, readers should not place undue reliance on forward-looking statements. The Company undertakes no obligation to update publicly or otherwise revise any forward-looking statements whether as a result of new information or future events or otherwise, except as may be required by law.

 

 

 

 

SOURCE Moneta Porcupine Mines Inc.

Ian C. Peres, President & CEO
416-579-3040 (Toronto) 
705-264-2296 (Timmins)
iperes@monetaporcupine.com


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Moneta Gold Inc.
Bergbau
-
-
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.