• Freitag, 15 November 2024
  • 19:37 Uhr Frankfurt
  • 18:37 Uhr London
  • 13:37 Uhr New York
  • 13:37 Uhr Toronto
  • 10:37 Uhr Vancouver
  • 05:37 Uhr Sydney

Prophecy Coal Debuts Its Power Division

07.08.2012  |  Marketwire

VANCOUVER, BRITISH COLUMBIA -- (Marketwire) -- 08/07/12 -- Prophecy Coal Corp. ("Prophecy" or the "Company") (TSX: PCY)(OTCQX: PRPCF)(FRANKFURT: 1P2) is pleased to debut Prophecy Power Corp. ("Prophecy Power"), the Company's wholly-owned Mongolian subsidiary focused on the power sector in Mongolia. Prophecy Power, formerly known as East Energy Corp, was incorporated in 2010 with the specific business objective of supplying power to Mongolia through the construction of the Chandgana Thermal Power Plant. Prophecy Coal's Chandgana LLC in parallel will develop the Chandgana coal project to ensure fuel supply to Prophecy Power.


Location


Prophecy Power's proposed 600 MW (150 MW x 4) mine mouth power plant complex is to be built next to Prophecy Coal's Chandgana coal deposit located in Central Mongolia, next to a paved highway, just 60 km from Undurkhann (east electricity grid connection leading to Cholbbalsan, and 120 km from Baganuur (west electricity grid connection leading to Ulaan Baatar).


Power Plant Licenses


Prophecy Power obtained approval of its Environmental Impact Assessment (EIA) from the Ministry of Nature and Tourism in November of 2010. In November 2011, the Ministry of Natural Resources and Energy granted a construction license for the 600 MW power plant. This license was the first of its kind ever granted in Mongolian history.


Directors and Management


Prophecy Power's Board of Directors consists of Chris Kwan, John Lee, and Bailikhuu Dambachultem.


Mr. Kwan is a lawyer with extensive experience with Power Purchase Agreements. Mr. Bailikhuu Dambachultem is an established Mongolian person whose previous posts included State Secretary and Advisor to numerous government agencies that manage power plants and other significant facilities in Mongolia. John Lee is the Chairman and CEO of Prophecy Coal and an entrepreneur with a home base in Ulaanbaatar. Mr. VP Sharma is appointed as Prophecy Power's advisor. Recently retired from a Director of Operations and Construction position with China Light and Power (CLP), Mr. Sharma is a Chartered Engineer with over 40 years in the Energy Industry.


Power Purchase Agreement ("PPA")


Since Prophecy Power obtained the construction license in November 2011, the Company has been in ongoing discussions with the Mongolian government to finalize a PPA in order to secure Mongolia's long-term energy supply, and enable project financing and construction to move forward.


The Ministry of Natural Resources and Energy appointed a working group of over a dozen experts on the legal, technical and commercial aspects of granting a PPA to Prophecy Power. In the last six months, Prophecy Power has held numerous sessions with working group members to establish Prophecy's Chandgana project status as the first independent power plant in Mongolia. Technical discussions included understanding and overcoming concerns over grid connection and plant implementation. Commercial discussions revolved around establishing tariff structure (cost plus principle, and take-or-pay) as well as the setting of prices (with proper indexation of fuel, operation & maintenance, and equity) that are both affordable and lower than current Russian power imports, yet generate a fair equity return to Prophecy Power's investors and shareholders. Equity risk assessment included Mongolian sovereign ratings and early stage development in the independent power sector. Prophecy expects to make a formal tariff submission in August and expects a reply in 2012.


In parallel, Prophecy Power has been in discussions with several private Mongolia companies regarding bi-lateral power purchase agreements. The current proposed mining projects (copper, molybdenum, and iron ore) and industrial development complex (cement and smelter) in Mongolia will, collectively, require up to 200 MW of power by 2016. This excludes the massive Oyu Tolgoi project. The remaining power supply from Prophecy Power's Chandgana Power Plant is expected to help meet the increasing energy demand created by ongoing expansion of Eastern and Northern Mongolia, and the capital city of Ulaanbaatar, as well as to replace Russian power imports.


Coal Supply Agreement


A coal supply agreement is in place whereby Chandgana LLC, another Prophecy wholly-owned Mongolian subsidiary, will supply 3 million tonnes of coal per year to Prophecy Power for 25 years. The initial coal price will be set with annual price adjustment based on diesel price, Mongolia's CPI and US' CPI. Chandgana LLC controls over 1.4 billion tonnes of thermal coal in measured and indicated categories, including a starter pit with 140 million tonnes of measured resource and a strip ratio of 0.5 to 1 which is ready to be mined. Upon the acquisition of the Tethys claims (refer to press release dated June 18, 2012) with a historic (non 43-101 compliant) resource estimate(i) of 2.3 billion tonnes, Chandgana LLC will control one of largest thermal coal basins in the world, with an ample supply of coal for a power plant of 4,200 MW or bigger.


Engineering, Procurement and Construction ("EPC") of Thermal Power Plant


In December 2011, Prophecy Power prepared a data room and distributed a request for proposal (RFP) to six carefully-selected EPC contractors. Site visits and technical sessions were conducted in Mongolia between January and May 2012. Prophecy received proposals from all six EPC contractors and in July, after extensive review and face-to-face meetings, Prophecy shortlisted three EPC contractors based on construction capability, equipment quality, time to deployment and price. Prophecy Power is currently in close discussions with the remaining candidates with respect to detailed design specifications, labor and parts requirements, Mongolian customs and import, and project timeline in order to formulate final quotes. Prophecy Power expects to finalize the EPC selection by October 1, 2012.


Project Financing and Financial Advisors


Prophecy Power is in active Project Financing discussions with a number of interested parties.


Financing structure is expected to be 30% equity and 70% debt. The 600 MW project will be implemented in two phases, with Phase 1 construction of 150 MW x 2 and the transmission lines planned to start in Q2, 2013 and be complete by early 2016. Phase 2 construction of 150 MW x 2 is planned to commence in 2014 and be completed in 2017.


Debt Financing


Prophecy Power has held preliminary discussions with China Export-Import Bank and Sinosure. There is a likelihood of Chinese financing predicated on a Chinese EPC and Chinese equity. Separately, Prophecy has approached EBRD and a number of major commercial banks active in Mongolia that have expressed interest in the Chandgana project. The risk-sharing provisions and investment returns detailed in the PPA will be an important factor in determining the financing arrangement.


Equity and Developer JV Financing


Prophecy has been introduced to a number of international power project developers ("Developers") since late 2011. Over ten Developers have executed Confidentiality Agreements and reviewed Prophecy Power's data room in looking to establish equity stakes in Prophecy Power and jointly construct, manage and operate the Chandgana Power Plant. Several Developers are at term sheet stage with Prophecy Power that will structure the sharing of Prophecy Power's expenses through various milestones such as PPA, financing close, and construction. The Developers have demonstrated genuine interests in partnering with Prophecy after learning more about Mongolia's acute power shortage after years of rapid growth, the Government's efforts toward liberalizing the energy sector, and the secured fuel supply from the Chandgana coal project. Prophecy's goal is to secure Developer sponsorship in 2012.


Prophecy Power is also in discussions with EPC contractors to obtain funds through an equity stake and/or advanced credit line to ensure construction starts in 2013 as planned.


Financial Advisors


Prophecy has met with several first-tier investment banks with interests in mining and utilities operations. While the Chandgana project is currently considered "greenfield", it has advanced to a mature stage for financial advisory engagement in 2012.


Prophecy's Chairman and CEO, John Lee, states: "The Company is entering into an exciting phase with several important near-term catalysts. Our international team, consisting of members of eight different nationalities, has been working tirelessly to conclude/finalize EPC selection, PPA, Developer JV, and Financing. Just last week, India suffered the most extensive power blackout in history, during which 600 million people faced rail shutdown, traffic gridlock and dangerous daytime heat without air conditioning. In Mongolia, the citizens would face a serious threat without power in -40 degree winter conditions. We have been mandated by the Mongolian Energy Authority to supply power by 2016 and we intend to fulfil this important mission."


Prophecy Power's Chandgana power project is the most mature thermal power project in Mongolia. Ground leveling work is to start in September in preparation for the pouring of foundation to commence in the spring of 2013.


(i) According to records reviewed by Prophecy, Tethys applied on March 15, 2011 to register a resource estimate of 2.33 billion tonnes of thermal coal for the Tugalgatai licenses with the Minerals Resource Council of Mongolia. The resources registered by Tethys are not NI 43-101 compliant.


About Prophecy Coal


Prophecy Coal Corp. is a Canadian listed company engaged in developing energy projects in Mongolia. The Company's wholly-owned subsidiary Prophecy Power is developing a proposed 600 MW mine-mouth power plant, which has been permitted by the Mongolian government, adjacent to its Chandgana coal deposit. Negotiations on financing, power purchase agreement and construction management are underway.


Mineral resources that are not mineral reserves do not have demonstrated economic viability.


Further information on Prophecy Coal can be found at www.prophecycoal.com.


ON BEHALF OF THE BOARD OF PROPHECY COAL CORP.


JOHN LEE, CEO/Chairman


Forward Looking Statements: This news release includes certain statements that may be deemed "forward-looking statements". All statements in this release, other than statements of historical facts, including, without limitation, statements regarding future plans and objectives of the companies are forward-looking statements that involve various risks and uncertainties. Although Prophecy believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Forward-looking statements are based on a number of material factors and assumptions. Factors that could cause actual results to differ materially from those in forward-looking statements include general economic, regulatory, market or business conditions, and other risks detailed herein and from time to time in the filings made by the companies with securities regulators. Mineral exploration and development of mines is an inherently risky business and large infrastructure projects such as power plants require huge amounts of capital which may not be available to Prophecy on terms which will allow its shareholders to realize a reasonable return or on any terms at all. Accordingly the actual events may differ materially from those projected in the forward-looking statements. For more information on Prophecy and the risks and challenges of its business, investors should review filings that are available at www.sedar.com.


Neither the TSX nor its Regulation Services Provider (as that term is defined in the policies of the TSX) accepts responsibility for the adequacy or accuracy of this release.

Contacts:

Prophecy Coal Corp.

Chris Ackerman

Manager, Investor Relations

1-800-459-5583
cackerman@prophecycoal.com
www.prophecycoal.com


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Silver Elephant Mining Corp.
Bergbau
A3DWAL
CA82770L3074
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.