Intrepid Mines Limited Releases Activities Report for the First Quarter THREE MONTHS TO 31 MARCH 2011

28.04.2011  |  Marketwire

THREE MONTHS TO 31 MARCH 2011

TORONTO, ONTARIO -- (Marketwire) -- 04/28/11 -- Intrepid Mines Limited (TSX: IAU)(ASX: IAU) (the 'Company') is pleased to announce the release of its report for the quarter ended 31 March 2011 regarding mining production, development and exploration activities, as required under ASX listing Rule 5.1.1, as well as the Company's Management's Discussion and Analysis and Interim Financial Report for the quarter ended 31 March 2011.


The documents are available on the Company's website (www.intrepidmines.com), will be available shortly with Intrepid's filings on Sedar (www.sedar.com) and can be reviewed on the ASX website (www.asx.com.au).


All dollar values are United States Dollars unless otherwise stated.


OVERVIEW


Finance



-- Group loss after tax for the three months ended 31 March 2011 of $3
million (unaudited) - includes discontinued operations.

-- The sale of Paulsens to Northern Star, which completed in July 2010, was
for a purchase consideration of up to A$40 million. The Group received
the two top-up payments of A$2.5 million each during the quarter,
bringing the total consideration up to the A$40 million maximum.

-- Interest income during the quarter was $1,547,000.

-- During the quarter 3,607,725 options to acquire shares in the Company
were exercised.

-- Cash balance and term deposits at quarter end totalled $181.088 million.


Operations



-- At Tujuh Bukit the ongoing drilling results from the underlying porphyry
copper-gold-molybdenum mineralisation are particularly encouraging and
there is an emerging picture of a very large porphyry system with zones
of particularly high grades and elevated gold-copper ratios.


Tujuh Bukit Oxide



-- On 2 February 2011, the Company announced that the technical report
entitled 'Tujuh Bukit Project Report on Mineral Resources' dated January
2011, has been filed on SEDAR (www.sedar.com) as well as with the ASX
(www.asx.com) (see the Company's news release of 14 December 2010 for a
summary of the oxide resource update). The report was prepared by
independent consultants Hellman and Schofield Pty. Ltd. in accordance
with the JORC Code and Canadian NI 43-101. It details an updated
Inferred Resource estimate of 130 million tonnes at 0.55 g/t gold and 18
g/t silver above a 0.2 g/t gold cut-off, for 2.4 million ounces of
contained gold and 80 million ounces of contained silver within the
combined oxide zones of the Tumpangpitu area of the Tujuh Bukit Project
in Indonesia.

-- On 20 April 2011, subsequent to the quarter end, the Company reported
the results of a Preliminary Economic Assessment ('PEA'), independently
prepared by Kappes Cassiday of Reno, Nevada, for a potential heap leach,
open pit gold mine on the oxide resource of the Tumpangpitu area. Based
on conservative assumptions, the PEA demonstrated a life of project
annual average production of 143,000 recovered ounces of gold for 9
years at a cash cost of US$376 per ounce, net of silver credits at
US$16.50 per ounce. The project delivers a post-tax cumulative cashflow
of US$445 million, an NPV (at a 10% discount rate) of US$180 million and
an IRR of 31%, at a gold price of US$1,050 per ounce. The Company's
board has approved immediate progress towards commencement of a pre-
feasibility study to be conducted in parallel with the advancement of
the forestry approval process.


Tujuh Bukit Porphyry



-- On 31 January 2011, the Company announced that drilling results for the
copper-gold porphyry had identified extensions to the known
mineralisation.

-- On 3 March 2011, the Company reported that assay results received from
five deep exploratory drill holes intercepted additional mineralisation
adjacent to and south of the main Tumpangpitu porphyry Inferred Resource
area. Together, diamond drill holes GTD 178, 181, 182, 183 and 184
confirm the clear potential for the expansion of the Tumpangpitu
porphyry.

-- An updated porphyry resource estimate is due in May which will
incorporate further deep drilling around the main Tumpangpitu copper-
gold porphyry zone. The initial resource, published in September 2010,
contained 500 million tonnes at 0.4% copper and 0.5g/t gold.


FORESTRY ACTIVITIES


The Indonesian Forestry Law restricts non forestry activities within protection forests and prohibits mining using an open pit method in protection forest areas. Accordingly, Intrepid's Alliance partner, PT IMN, is working with relevant Indonesian authorities regarding a potential review of forest land status. While similar reviews have led to the granting of reclassifications, there is no assurance that the forestry reclassification will take place in this instance.


Qualified Person


The information in this report that relates to exploration results at Tujuh Bukit is based on information compiled by or under the supervision of Mr Norris, who is a member of The Australasian Institute of Mining and Metallurgy. Malcolm Norris is a full-time employee of Intrepid Mines Limited and has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves' and is a Qualified Person as defined in the Canadian National Instrument 43-101 (standards of Disclosure for Mineral Projects). Malcolm Norris consents to the inclusion in this announcement of the matters based on his information in the form and context in which it appears.


The information in this announcement that relates to mineral resources at Tujuh Bukit is based on information compiled by or under the supervision of Dr Phillip Hellman, who is an independent consultant to Intrepid Mines Limited. Dr Hellman has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as an Independent Competent Person as defined in the 2004 Edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves' and an Independent Qualified Person as defined in the Canadian National Instrument 43-101 (standards of Disclosure for Mineral Projects). Dr Hellman consents to the inclusion in this announcement of the matters based on his information in the form and context in which it appears.


The PEA was prepared by independent industry consultants, all qualified persons under Canadian National Instrument 43-101. The following consultants and qualified persons participated in the PEA:



-- Kappes Cassiday and Associate, under the direction of Daniel Kappes,
PEng. Mr Kappes is the President of KCA. He supervised and reviewed the
heap leach pad and solution ponds design, process design and
infrastructure requirements, capital and operating cost estimate, and
financial analysis of this project.
-- Australian Mine Design and Development Pty Ltd., under the direction of
Peter Allen, MAusIMM. Mr. Allen is an open pit engineering and principal
consultant at AMDAD Pty Ltd. He supervised and reviewed all the mining
design aspects of this project.


An NI 43-101-compliant technical report will be filed on SEDAR within 45 days of the date of release of this announcement.


FORWARD-LOOKING STATEMENTS


This announcement contains certain forward-looking statements relating to, but not limited to, Intrepid's expectations, intentions, plans and beliefs. Forward-looking information can often be identified by forward-looking words such as 'anticipate', 'believe', 'expect', 'goal', 'plan', 'intend', 'estimate', 'may' and 'will' or similar words suggesting future outcomes, or other expectations, beliefs, plans, objectives, assumptions, intentions or statements about future outcomes, or statements about future events or performance. Forward-looking information may include reserve and resource estimates, estimates of future production, unit costs, costs of capital projects, and timing of commencement of operations and is based on current expectations that involve a number of business risks and uncertainties. Factors that could cause actual results to differ materially from any forward-looking statement include, but are not limited to, failure to establish estimated resources and reserves, the grade and recovery of ore which is mined varying from estimates, capital and operating costs varying significantly from estimates, delays in obtaining or failures to obtain required governmental, environmental or other project approvals, inflation, changes in exchange rates, fluctuations in commodity prices, delays in the development of projects and other factors. Forward-looking statements are subject to a variety of known and unknown risks, uncertainties and other factors that could cause actual events or results to differ materially from those expressed or implied.


Shareholders and potential investors are cautioned not to place undue reliance on forward-looking information. By its nature, forward-looking information involves numerous assumptions, inherent risks and uncertainties, both general and specific, that contribute to the possibility that the predictions, forecasts, projections and various future events will not occur. Intrepid undertakes no obligation to update publicly or otherwise revise any forward-looking information whether as a result of new information, future events or other such factors which affect this information, except as required by law.


Statements relating to gold reserve and resource estimates are expressions of judgment, based on knowledge and experience and may require revision based on actual production experience. Such estimates are necessarily imprecise and depend to some extent on statistical inferences and other assumptions, such as gold prices, cut-off grades and operating costs, which may prove to be inaccurate. Information provided relating to projected costs, capital expenditure, production profiles and timelines are expressions of judgment only and no assurances can be given that actual costs, production profiles or timelines will not differ materially from the estimates contained in this announcement.


ABN: 11 060 156 452

Contacts:

Intrepid Mines Limited

Brad Gordon

CEO

Brisbane Australia

61 7 3007 8011
bgordon@intrepidmines.com


Intrepid Mines Limited

Greg Taylor

Toronto Canada

905 337-7673 / Mob: 416 605-5120
gtaylor@intrepidmines.com


Intrepid Mines Limited

Level 1, 490 Upper Edward Street

Spring Hill QLD 4004, Australia
www.intrepidmines.com



Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Intrepid Mines Ltd.
Bergbau
-
-
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.