Auriant Mining AB (publ.) publishes Q1 2022 operational update

20.04.2022  |  Globenewswire Europe

Highlights:

  • In Q1 2022, hard rock gold production amounted to 216.7 kg (6,967 oz), compared to 209.7 kg (6,743 oz) in Q1 2021, an increase of 3%, or 7 kg (224 oz);
  • Due to the seasonality of the operations at Staroverinskaya (Solcocon), there was no alluvial gold production in the period, although 47 155 m3 of top soil was moved in Q1 2022 preparing access to the gold sands;
  • In Q1 2022, total gold sales were 292.1 kg (9,392 oz), compared to 180.0 kg (5,787 oz) in 3m 2021, an increase of 112.1 kg (3,605 oz), or 62%;
  • 96,268 tonnes of ore with an average grade of 2.44 g/t were processed through the CIL plant;
  • The CIL plant operated for 1,887 hours at an increased throughput rate of 51 tonnes per working hour (>50 t/hour) and at the targeted recovery rate of 91.2%;
  • 51,090 tonnes of ore were mined in Q1 2022, compared to 26,190 tonnes in Q1 2021, an increase of 24,900 tonnes or 95%. Stripping volume amounted to 528,200 m3 (+115,600 m3, or 28% more than in Q1 2021);
  • The average grade in Q1 2022 was 2.44 g/t, compared to 2.04 g/t in Q1 2021, an increase of 20%;

Overall, Q1 2022 production was in line with the Company's production plan.

Others:

  • In regards to the current challenging geopolitical situation, although operations at Tardan have been unaffected, the Company has decided to widen its gold sales channels.
    • Three new sales contracts with refinery plants were signed.
    • The Company's subsidiary has applied for an export license to be able to sell gold outside Russia.
    • There is an option of selling gold to a new bank under a new sales contract.

Despite the current restrictions and the challenging market environment, the Company's subsidiaries continue to sell gold, but with discounts to the LBMA gold price that can be substantial. The effect of these discounts is to some extent mitigated by the strong gold price and the weak Ruble.

Total Gold Production

Production unit 3m 2022 3m 2021 Change
kg oz kg oz kg oz %
Hard rock
Tardan (CIL) 216.7 6,967 209.7 6,743 7.0 224 3%
Alluvial
Staroverinskaya - - - - - - -
Total gold produced 216.7 6,967 209.7 6,743 7.0 224 3%

Hard Rock Gold Production

Unit 3m 2022 3m 2021 Change
Mining
Waste stripping 000 m3 528.2 412.6 115.6 28%
Ore mined 000 tonnes 51.1 26.2 24.9 95%
Gold in Ore kg 134.5 63.4 71.2 112%
Average grade g/t 2.63 2.42 0.21 9%
CIL
Ore processing 000 tonnes 96.3 96.2 0.0 0%
Grade g/t 2.44 2.04 0.40 20%
Gold in ore processing kg 235.2 196.5 38.7 20%
Gold produced CIL kg 216.7 209.7 7.0 3%
Opening WIP (gold) kg 5.2 27.9
Closing WIP (gold) kg 2.9
Recovery % 91.18% 92.5% -1.4% -1.5%
Warehouse on Mar 31
Ore 000 tonnes 86.4 31.3 55.0 176%
Grade g/t 2.16 2.30 - 0.14 -6%

For more information, please contact:

Danilo Lange, CEO
Tel: +7 495 109 02 82
E-mail: d.lange@auriant.com

Company name: Auriant Mining AB Short name: AUR
ISIN-code: SE0001337213

Website: www.auriant.com
www.facebook.com/AuriantMining/

Auriant Mining AB (AUR) is a Swedish junior mining company focused on gold exploration and production in Russia, primarily in the Republic of Tyva, Zabaikalye and the Republic of Khakassia. The company has currently four assets, including two operating mines (Tardan and Alluvial at Staroverinskaya), one early stage exploration asset and one development asset.

Since July 19, 2010, Auriant Mining´s shares are traded on Nasdaq First North Premier Growth Market under the short name AUR. For more information, please visit www.auriant.com. G&W Fondkommission is Certified Adviser to Auriant, for more information please call +46 8 503 000 50, e-mail CA@gwkapital.se or visit www.gwkapital.se.

This information is information that Auriant Mining AB is obliged to make public pursuant to the EU Market Abuse Regulation. The information was submitted for publication, through the agency of the contact persons set out above, at 15.35 CET on April 20th, 2022.

Attachment

  • Q1_2022_Press release (Operational)_ENG


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Auriant Mining AB
Bergbau
A0EACA
SE0001337213
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.