• Mittwoch, 25 Dezember 2024
  • 18:12 Uhr Frankfurt
  • 17:12 Uhr London
  • 12:12 Uhr New York
  • 12:12 Uhr Toronto
  • 09:12 Uhr Vancouver
  • 04:12 Uhr Sydney

Wiluna Mining Corporation Ltd: Wiluna Mine Progress Update

22.03.2022  |  ABN Newswire
Perth, Australia - Wiluna Mining Corp. Limited (ASX:WMC) (FRA:NZ3) (OTCMKTS:WMXCF) is pleased to provide an update on ramp-up production of gold concentrate at its Wiluna Mine.

HIGHLIGHTS

- Ramp-up into its third month, concentrator performing ~25% above nameplate

- Since ramp-up, 3,855 tonnes of gold concentrate produced (7,800 ounces) at an average grade of 69.9 g/t, three shipments and 4,488 ounces have been dispatched

- Underground mine production constrained to 70% of target due to COVID and manning issues associated with the general skills shortage, which will delay the ramp-up to declared commercial production from end of June to the second half of CY'2022

- WilTails now scheduled to commence in late May; expected to produce ~1,250 ounces per month

The commissioning of the concentrator took place in December 2021. This commissioning was successful and the ramp-up to commercial production effectively commenced on 1 January 2022 and was expected to take approximately six months to achieve commercial production of approximately 8,000 ounces per month. WMC's WilTails treatment facility was expected to commission in February 2022 and add approximately 1,250 ounces of production per month with minimal ramp-up time.

Due to already reported COVID-related supply constraints that further reduced skilled labor availability, and delayed approvals that have now been received, WilTails commissioning has been delayed until late May 2022 with full production expected by July 2022. Upon achieving full commercial production, the concentrator and WilTails (Stage 1) are expected to produce 110k-115kozpa.

Explanation

Mining is currently development-focused which comprises lower grade ore and waste material. Mining of stope ore has commenced and will increase over the coming months. Currently, mining is at 53% of stope ore with 47% of lower-grade development ore. The plan is to increase the percentage of stope ore mined to 80% which will increase the head grade of the mined material being processed. Average grade of ore delivered to the mill is currently ~2.7 g/t, which is lower than was scheduled, however, it is scheduled to increase to 3.5 g/t in the medium term and to over 4 g/t at steady-state production.

Ramp-up has also been impacted by manning issues within the underground mining team over the entire ramp-up period, and particularly in the past two weeks COVID which has restricted our mining team to approximately 70% of its capacity.

We expect these issues will continue to affect production for at least the next three months, and this will most likely delay declaration of commercial production which was expected to be the end of June 2022. We are now expecting that full commercial production will not be achieved until the second half of CY'2022.

Production is expected to be approximately 11,000 ounces for the March quarter and approximately 4,000 ounces per month for the next two months (April and May) before ramping up to 8,000 ounces per month in concentrate by the second half of CY'2022, with an additional 1,250 ounces per month of gold dore from tailings retreatment commencing in July. The concentrator is performing above nameplate, and it is processing between 900,000-950,000 tonnes per annum against a nameplate 750,000 tonnes per annum. This will provide opportunity to optimise production as mine production increases.

*To view tables and figures, please visit:
https://abnnewswire.net/lnk/1V73WSWF



About Wiluna Mining Corporation Ltd:

Wiluna Mining Corp. (ASX:WMC) (OTCMKTS:WMXCF) is a Perth based, ASX listed gold mining company that controls over 1,600 square kilometres of the Yilgarn Craton in the Northern Goldfields of WA. The Yilgarn Craton has a historic and current gold endowment of over 380 million ounces, making it one of most prolific gold regions in the world. The Company owns 100% of the Wiluna Gold Operation which has a defined resource of 8.04M oz at 1.67 g/t au. In May 2019, a new highly skilled management team took control of the Company with a clear plan to leverage the Wiluna Gold Operation's multi-million-ounce potential.



Source:
Wiluna Mining Corp. Ltd



Contact:

Milan Jerkovic Executive Chair +61 8 9322 6418 Jim Malone General Manager Investor Relations +61 419 537 714 Dannika Warburton Media & Communications +61 401 094 261


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Wiluna Mining Corp.
Bergbau
A3CXT0
AU0000164139
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.