• Freitag, 15 November 2024
  • 20:19 Uhr Frankfurt
  • 19:19 Uhr London
  • 14:19 Uhr New York
  • 14:19 Uhr Toronto
  • 11:19 Uhr Vancouver
  • 06:19 Uhr Sydney

Katanga Mining Announces 2017 Fourth Quarter and Year End Financial Results

03.04.2018  |  CNW

ZUG, Switzerland, April 2, 2018 /CNW/ - Katanga Mining Limited (TSX: KAT) ("Katanga" or the "Company") today announces its financial results for the fourth quarter and 2017 fiscal year. Katanga's Financial Statements and Management's Discussion and Analysis will be filed on SEDAR, www.sedar.com.







Three months ended

Years ended



Dec 31,

Sep 30,

Dec 31,

Dec 31,

Dec 31,



2017

2017

2016

2017

2016

Financial







Total sales*

$'000

7,696

5,875

3

25,292

(30,127)

 - including repricing*

$'000

265

(169)

3

99

(30,853)

Cost of sales

$'000

(4,289)

(3,031)

-

(31,839)

-

Gross profit (loss)

$'000

3,407

2,844

3

(6,547)

(30,127)

Net loss attributable to
shareholders

$'000

(230,657)

(115,362)

(113,219)

(573,496)

(419,887)

Cash flows used in operating
activities

$'000

(71,844)

(56,745)

(7,089)

(172,487)

(161,080)

EBITDA**

$'000

(187,587)

(69,091)

(64,468)

(382,748)

(238,745)








Mining







Waste mined

tonnes

11,193,159

14,358,022

2,152,986

45,294,775

8,174,964

Ore mined

tonnes

433,169

-

-

433,169

825

Average copper grade

%

2.18

-

-

2.18

2.67

Contained copper in ore mined

tonnes

9,459

-

-

9,459

22








KTC







KITD material milled

dmt

481,617

586,664

-

1,758,890

-

KITD copper contained in
concentrate

dmt

5,061

4,972

-

14,912

-

KOV Open pit ore milled

tonnes

163,211

-

-

163,211

-

KOV Open pit ore grade

%

4.05

-

-

4.05

-








 

Luilu







WOL feed - KITD concentrate

dmt

13,755

-

-

13,755

-

WOL feed - open pit ore

dmt

126,471

-

-

126,471

-

Finished copper

tonnes

2,196

-

-

2,196

-

Finished cobalt

tonnes

-

-

-

-

-









*         

Negative price and sales amounts are a result of quality discounts, adverse repricing and marked-to-
market ("M2M") adjustments

**      

Refer to item 23 Non-IFRS financial measures. Due to the suspension of production C1 cash costs
are not calculated for this period.

 

Commissioning and resumption of production

  • On September 11, 2015 the Company announced the decision to suspend the processing of copper and cobalt during the construction phases of the whole ore leach project ("WOL Project"). The suspension continued through 2017 with copper production resuming on December 11, 2017;
  • Commissioning of phase 1 of the WOL Project was completed in November 2017 and the first copper cathode was produced on December 11, 2017;
  • Phase 2 construction activities of the WOL Project have continued and are progressing according to the 2018 project execution plan. Full commissioning of the WOL Project is expected in Q4 2018; and
  • Mining operations continued during 2017 at the KOV open pit mine ("KOV Open Pit") and Mashamba East open pit mine, still focusing on waste stripping.

Review of 2017 Fourth Quarter Results

Financial

Profitability during Q4 2017, when compared to Q3 2017 and Q4 2016, was affected by:

  • Sales of 451 tonnes of finished copper cathode which represents a $3.3 million increase over Q3 2017 during which period there were no finished copper cathode sales;
  • During Q4 2017, the Company sold 1,915 tonnes of copper contained in the Kamoto interim tailings dam ("KITD") oxide concentrate to Mutanda Mining SARL ("Mutanda"), which resulted in revenues of $4.5 million (Q3 2017 - $5.9 million); The production of KITD concentrates used for the ramp-up of operations in Q4 2017 will continue and the Company does not expect to make any further sales of concentrate in 2018;
  • Cost of sales relating to the sale of copper cathode and copper concentrate was driven by metal stock movement amounting to $4.3 million in Q4 2017 (Q3 2017 - $3.0 million; Q4 2016 – $nil);
  • EBITDA for Q4 2017 was a loss of $187.6 million compared to a loss of $64.5 million for Q4 2016. Increased losses arose due to an increase in mine infrastructure, ramp-up and support care and maintenance costs, including higher diesel, mechanical spares and personnel costs; and
  • Net loss attributable to shareholders for Q4 2017 was $230.7 million compared to a loss of $113.2 million for Q4 2016. In addition to the items noted in EBITDA, the increased net loss in Q4 2017 resulted from higher depreciation, and interest.
  • Cash flow used in operating activities was $71.8 million in Q4 2017, and $7.1 million in Q4 2016.

Mining

  • Waste mined in Q4 2017 was 11,193,159 tonnes, which was 9,040,173 tonnes (419.9%) higher than Q4 2016. The increase was due to greater waste mining activities in 2017, carried out in preparation for the commissioning of the WOL Project, phase 1 of the core circuit which was completed in November 2017;
  • Following the commissioning of phase 1 of the WOL Project, the resumption of copper production and ore mining commenced in Q4 2017. Ore mined at the KOV Open Pit Mine ("KOV Open Pit") during Q4 2017 was 433,169 tonnes with an average copper grade of 2.18%, resulting in contained copper of 9,459 tonnes. In 2016, ore mined was 825 tonnes at KOV Open Pit and was related to incidental ore mined during waste mining; and
  • In Q4 2017, the Company did not commission any new items of fleet.

Processing

  • KITD material milled for Q4 2017 at the Kamoto Concentrator ("KTC") was 481,617 tonnes, resulting in 5,061 tonnes of contained copper (oxides and sulphides). Copper contained in KITD oxide concentrate of 1,915 tonnes was sold to Mutanda in Q4 2017;
  • The total tonnes milled at KTC were 644,828 for Q4 2017, split between 481,617 tonnes of KITD material and 163,211 tonnes of KOV open pit ore;
  • Of the 163,211 tonnes of KOV open pit ore milled, 36,740 tonnes were used to commission the milling circuit and flotation circuit at KTC.;
  • Material processed by Luilu Metallurgical Plant ("Luilu") after commissioning was 140,226 tonnes, of which 126,471 was KOV open pit ore tonnes and 13,755 was KITD oxide concentrate tonnes, which resulted in production of finished copper of 2,196 tonnes;
  • In Q4 2017, the Company re-commissioned the following assets at KTC:
    • B3 crusher for crushing capacity;
    • CM1, CM4, BM1 and BM3 for milling capacity; and
    • Flotation banks 801, 821, 802 and 803 for flotation capacity.
  • In Q4 2017, the Company commissioned:
    • A new pump station for the hydro-mining activities at KITD, to facilitate a production increase from 300tph to 500tph;
    • The core copper circuit of phase 1 WOL plant at Luilu;
    • A new metallurgical accounting system; and
    • Two new pipelines from KTC and Luilu for the deposit of tailings into the Mupine tailings storage facility.
  • During Q4 2017, the Company completed the following work on the WOL Project:
    • Construction of the receiving thickener, core copper circuit counter current decantations, leach plant, high grade clarifier for the first phase of WOL Project and PLS and raffinate ponds for the first and second phase of WOL Project. The required modifications to the existing solvent extraction and electro- winning plants for first copper production in Q4 were also completed. Key services such as gland seal water, flocculant and lime plants were also installed and commissioned;
    • The fibre communication network, SCADA (Supervisory Control and Data Acquisition software used for automated control of the plant), electrical and instrumentation equipment were installed and commissioned, allowing for plant start-up in November 2017;
    • Related capital expenditures amounted to $53.1 million in Q4 2017;
    • Concurrent with the construction of the WOL project plant and infrastructure, the current Life of Mine plan continues to be optimized to ensure the appropriate blend will be supplied to the WOL process in order to maximize copper and cobalt recovery and to minimize operating costs per unit; and
    • Design work progressed during Q4 2017 on the acid plant (the "Acid Plant"), cobalt de-bottlenecking and cobalt dryer projects. The Acid Plant is a sulfuric acid and sulfur dioxide production plant expected to be constructed at the mine site owned by the Company's 75% subsidiary Kamoto Copper Company ("KCC"), which will improve the reliability of the supply of these reagents to the WOL Project processing circuit. The Acid Plant is designed to produce 1,900 tpd of sulfuric acid, 200 tpd of sulfur dioxide and 17MW of co-generated power. This will reduce KCC's reliance on imported volumes of reagents brought to the mine through various international borders.

Review of 2017 Full Year Results

Financial

Profitability during 2017, when compared to 2016, was affected by the following:

  • Sales of 451 tonnes of finished copper cathode which represented a $3.3 million increase over 2016 during which no copper cathode was produced. However, the Company has sales of negative $30.1 million in 2016 due to quality discounts;
  • Sales of 2,746 tonnes of copper contained in KITD oxide concentrate and 5,862 tonnes from site clean up amounting to $22.3 million sold to Mutanda (2016 - $nil);
  • Cost of sales relating to the sale of copper cathode and copper concentrate is driven by metal stock movement amounting to $31.8 million in 2017 (2016 – $nil). The business rationale for selling the concentrate was to reduce working capital by liquidating inventory on hand that would otherwise not be processed in the short term to produce more profitable copper cathode. This led to gross loss on copper concentrate sold. The production of KITD concentrates used for the ramp-up of operations in Q4 2017 will continue and the Company does not expect to make any further sales of concentrate in 2018;
  • EBITDA for the year ended December 31, 2017 was a loss of $382.7 million compared to a loss of $238.7 million for the year ended December 31, 2016. This was due to the increased costs associated with mining and general ramp-up, ahead of WOL Project commissioning; and
  • Net loss attributable to shareholders for the year ended December 31, 2017 was $573.5 million compared to a loss of $419.9 million for the year ended December 31, 2016. In addition to the items noted in EBITDA, the increased net loss in the year ended 2017 was as a result of higher depreciation and interest expense.

Mining

  • Waste mined in 2017 was 45,294,775 tonnes, or 454.1% higher than 2016 driven by operational requirement to secure sufficient ore availability for the commissioning of the WOL Project, for which the core circuit of phase 1 was completed in Q4 2017; and
  • Following the commissioning of the core circuit of phase 1 of the WOL Project and resumption of copper production, ore mining commenced in Q4 2017. Ore mined at the KOV Open Pit Mine ("KOV Open Pit") during 2017 was 433,169 tonnes. The average copper grade of ore mined from KOV Open Pit was 2.18%, resulting in contained copper of 9,459 tonnes. In 2016, ore mined was 825 tonnes at KOV and is related to incidental ore mined during waste mining.

Processing

  • The total tonnes of KITD material milled in 2017 was 1,758,890 tonnes with 14,912 tonnes of contained copper produced (in oxide & sulphide concentrates). Copper contained in KITD oxide concentrate of 2,746 tonnes and copper derived from site clean-up of 5,862 tonnes was sold to Mutanda in 2017;
  • During 2017, work completed on the WOL Project included:
    • Construction of the acid storage tanks has been completed and progress continues on 'Structural, Mechanical, Platework and Piping ("SMPP") activities on the Receiving, Preleach, Leach and CCD trains. The SCADA (Supervisory Control and Data Acquisition software used for automated control of the plant), electrical and instrumentation equipment were installed and commissioned, allowing for plant start-up in November 2017; and
    • Related capital expenditures amounted to $189.6 million in 2017, which principally related to the installation of the SMPP, electrical, control and instrumentation equipment.
  • The total tonnes milled at KTC was 1,922,101 for 2017, split between 1,758,890 tonnes of KITD material and 163,211 tonnes of open pit ore;
  • Of the 163,211 tonnes of open pit ore milled, 36,740 tonnes were used to commission the milling circuit and flotation circuit at KTC;
  • Material processed by Luilu after commissioning was 140,226 tonnes, of which 126,471 tonnes was open pit ore and 13,755 tonnes was KITD oxide concentrate tonnes, which resulted in finished copper of 2,196 tonnes;
  • In Q4 2017, the Company re-commissioned the following assets at KTC:
    • B3 crusher for crushing capacity;
    • CM1, CM4, BM1 and BM3 for milling capacity; and
    • Flotation banks 801, 821, 802 and 803 for flotation capacity.
  • In 2017, the Company commissioned:
    • A new pump station for the hydro-mining activities at KITD, to facilitate production increase from 300tph to 500tph;
    • The core copper circuit of phase 1 WOL plant at Luilu;
    • A new metallurgical accounting system;
    • Two new pipelines from KTC and Luilu for the deposition of tailings into the Mupine tailings storage facility;
    • Six CAT 793 haul trucks at the KOV open pit mine; and
    • One CAT 6015 excavator at the KOV open pit mine.

Outlook

During 2018:

  • Open pit mining operations are expected to continue to feed ore to the run-of-mine stockpiles in accordance with the optimized ore blending strategy, and waste stripping in both KOV and Mashamba East open pits will continue;
  • Hydraulic backfill and care and maintenance activities at KTO underground operations are expected to continue to ensure operational readiness for underground operations resuming in future years;
  • Phase 2 construction activities on WOL Project to continue and are expected to progress according to the 2018 project execution plan;
  • KTC including KITD, and Luilu are expected to ramp-up the operations to produce copper and cobalt in accordance with the ramp-up plan;
  • Execution of the Acid Plant, cobalt dryers and cobalt de-bottlenecking projects are expected to continue to ensure the completion of the planned project schedules;
  • The Company reiterates its 2018 production guidance of 150,000 tonnes and 11,000 tonnes of copper cathode and cobalt contained in hydroxide respectively; and
  • Various continuous improvement initiatives relating to production enhancement and consumable inventory reduction are expected to be implemented to ensure the efficiency of operations.

Qualified Person

Tahir Usmani, PEng, APEGA, Chief Mine Planning Engineer of KCC, has reviewed and approved the scientific and technical disclosure in this news release. Mr. Usmani is a "qualified person" for the purposes of NI 43-101 - Standards of Disclosure for Mineral Projects.

About Katanga Mining Limited
Katanga Mining Ltd. operates a major mine complex in the Democratic Republic of Congo producing refined copper and cobalt. The Company has the potential to become Africa's largest copper producer and the world's largest cobalt producer. Katanga is listed on the Toronto Stock Exchange under the symbol KAT.

Forward Looking Statements
This press release may contain forward-looking statements. Often, but not always, forward-looking statements can be identified by the use of words such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or describes a "goal", or variation of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved.

All forward-looking statements reflect the Company's beliefs and assumptions based on information available at the time the statements were made. Actual results or events may differ from those predicted in these forward-looking statements. All of the Company's forward-looking statements are qualified by the assumptions that are stated or inherent in such forward-looking statements, including the assumptions listed below. Although the Company believes that these assumptions are reasonable, this list is not exhaustive of factors that may affect any of the forward-looking statements. The key assumptions that have been made in connection with the forward-looking statements include the following: the operations of the Company during the production suspension and timeline for the recommencement of operations remaining consistent with management's expectations, there being no significant disruptions affecting the operations of the Company whether due to labour disruptions, supply disruptions, power disruptions, rollout of new equipment, damage to equipment or otherwise; permitting, development, operations, expansion and acquisitions at the Project being consistent with the Company's current expectations; continued recognition of the Company's mining concessions and other assets, rights, titles and interests in the DRC; political and legal developments in the DRC being consistent with its current expectations; the continued provision or procurement of additional funding from Glencore for operations, the completion of the T17 Underground Mine, phase 2 of the the WOL Project and the Power Project (as defined in the Annual Information Form of the Company for the year ended December 31, 2016 dated March 31, 2017); that new equipment performs to expectations; the exchange rate between the US dollar, South African rand, British pounds, Canadian dollar, Swiss franc, Congolese franc and Euro being approximately consistent with current levels; certain price assumptions for copper and cobalt; prices for diesel, natural gas, fuel oil, electricity and other key supplies being approximately consistent with current levels; production, operating expenses and cost of sales forecasts for the Company meeting expectations; the accuracy of the current ore reserve and mineral resource estimates of the Company (including but not limited to ore tonnage and ore grade estimates); and labour and material costs increasing on a basis consistent with the Company's current expectations.

Forward-looking statements involve known and unknown risks, future events, conditions, uncertainties and other factors which may cause the actual results, performance or achievements to be materially different from any future results, prediction, projection, forecast, performance or achievements expressed or implied by the forward-looking statements. Such factors include, among others, the unforeseen delays or changes to the WOL Project; actual results of current exploration activities; actual results and interpretation of current reclamation activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; future prices of copper and cobalt; possible variations in ore grade or recovery rates; failure of plant, equipment or processes to operate as anticipated; accidents, labour disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing or in the completion of exploration, development or construction activities, delays due to strikes or other work stoppage, both internal and external to the Company as well as those factors disclosed in the Company's current annual information form and other publicly filed documents. Although Katanga has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements.

The Company disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events, or otherwise, except in accordance with applicable securities laws.

SOURCE Katanga Mining Ltd.



Contact
Johnny Blizzard, CEO, Tel: +41 (041) 766 71 10; Grant Sboros, CFO, Tel:+41 (041) 766 71 10
Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Katanga Mining Ltd.
Bergbau
-
-
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.