• Samstag, 28 Dezember 2024
  • 16:24 Uhr Frankfurt
  • 15:24 Uhr London
  • 10:24 Uhr New York
  • 10:24 Uhr Toronto
  • 07:24 Uhr Vancouver
  • 02:24 Uhr Sydney

Intermin Resources Limited: Teal Gold Mine continues to deliver

05.09.2017  |  ABN Newswire
Perth - Intermin Resources Ltd. (ASX:IRC) ("Intermin" or the "Company") provides the following operational update from Intermin's 100% owned Teal Gold Mine, located 11km north west of Kalgoorlie-Boulder in Western Australia (see Figure 2 in the link below).

HIGHLIGHTS

- Mining, ore haulage and processing continues successfully at the Teal open pit

- Ore mined to date totals 98,900t grading 3.20g/t for 10,160 ounces

- Gold recoveries remain at 94% for an estimated 9,550 ounces recovered to date (see Note 1 below)

- Repayment of Intermin's capital investment of $2.1m complete

- Return of Intermin's asset recovery charge of $2.15m expected this Quarter under the terms of the Mining Alliance (see Note 2 below)

- Teal on track to produce 15,000 - 16,000 ounces at All In Cost (AIC) of A$1,030 - A$1,090 per ounce generating total net cash flow to Intermin of $7m - $8m at a $1,600/oz gold price (see Note 3 below)

- Cash and investments to date (see Note 4 below) rise to more than $6m with mining completion of Stage 1 expected in the December Quarter 2017

Commenting on progress at Teal, Intermin's Managing Director, Mr Jon Price said:

"As Stage 1 at Teal continues to generate significant cash flow to the business, the Company is in an exciting growth phase as we complete Feasibility Studies on the Goongarrie Lady gold project and further stages at Teal to expand the production pipeline.

"The Company also expects ongoing drilling results from the self-funded 32,000m exploration program in coming months as we continue our Resource expansion efforts and the search for the next WA Goldfields discovery."

Overview

Mining continues in the southern section of the pit (see Figure 1 in the link below) with supergene oxide ore now exposed across the entire pit floor for load and haul through to completion in the December Quarter. The strip ratio for the remaining life of the project is 3:1 with total movement to date of 1.66MBCM. Ore mined to date from the project totals 98,900 dry tonne at an average grade to 3.20g/t, in line with Reserve model estimates.

Ore haulage to the third party mill for processing will occur at 10 - 15,000t per week with plant recoveries of 94% to date continuing to outperform the Feasibility Study estimates of 90% for the oxide ore component.

Contained metal mined to date totals 10,161 ounces and the project remains on track to meet guidance of 15,000 -16,000 ounces at an All in Cost (AIC) estimated at $1,030 - $1,090 per ounce (See Note 5 below).

Initial capital investment repayments of $2.1m have now been made to both RM Contracting and Intermin. The Company is expecting payment of the $2.15m asset recovery charge this Quarter prior to the profit share component in accordance with the Mining Alliance Contract (see Note 6 below).

Cash at bank (see Note 7 below) as of 5 September totals $4.9m and tradeable securities held total $1.14m.

Notes:

1 includes final and provisional data

2 as announced to the ASX on 19 July 2016

3 as announced to the ASX on 14 June 2017, see also Competent Persons Statement on page 3 and Forward Looking and Cautionary Statement on page 4.

4 includes actual and provisional amounts under the ore sales agreement announced to the ASX on 27 July 2017

5 as announced to the ASX on 14 June 2017, see also Competent Persons Statement on page 3 and Forward Looking and Cautionary Statements on page 4

6 as announced to the ASX on 19 July 2017.

7 includes final and provisional amounts under the Ores Sales Agreement as announced on 27 July 2017

To view tables and figures, please visit:
http://abnnewswire.net/lnk/2ZA6AI1U



About Intermin Resources Limited:

Intermin Resources Ltd. (ASX:IRC) is a gold exploration and mining company focussed on the Kalgoorlie and Menzies areas of Western Australia which are host to some of Australia's richest gold deposits. The Company is developing a mining pipeline of projects to generate cash and self-fund aggressive exploration, mine developments and further acquisitions. The Teal Stage 1 gold mine is currently in production.

Intermin is aiming to significantly grow its JORC-Compliant Mineral Resources, complete definitive feasibility studies on core projects and build a sustainable development pipeline.

Intermin is targeting the definition of significant high grade open cut and underground gold deposits, has acquired highly prospective tenure and will continue to actively pursue consolidation and value-adding joint venture opportunities for the benefit of all stakeholders.



Contact:

Intermin Resources Ltd.
Jon Price Managing Director
Tel: +61-8-9386-9534
E: jon.price@intermin.com.au

Lorry Hughes Director - Business Development
Tel: +61-8-9386-9534
E: lorry.hughes@intermin.com.au

Michael Vaughan Media Relations - Fivemark Partners
Tel: +61-422-602-720
E: michael.vaughan@fivemark.com.au

Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Horizon Minerals Ltd.
Bergbau
A2PPL5
AU0000053373
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.