Rambler Metals and Mining plc: Three Month Ending October 31, 2016 - Production Results

01.12.2016  |  Marketwire

BAIE VERTE, NL--(Marketwired - Dec 1, 2016) -  Rambler Metals & Mining PLC (TSX VENTURE: RAB) (LSE: RMM)

TSXV: RAB, AIM: RMM

1 December 2016

Three Month Ending October 31, 2016 - Production Results

London, England & Baie Verte, Newfoundland and Labrador, Canada - Rambler Metals and Mining plc (TSXV: RAB, AIM: RMM) ('Rambler' or the 'Company'), a copper and gold producer operating in Newfoundland and Labrador, Canada, today provides an operational update for the first quarter ended 31 October 2016 ('Q1/17 Stub').

Summary for Q1/17 Stub: Ore, Concentrate and Saleable Metal Production
         
PRODUCTION Q1 Stub/17   CONCENTRATE
(Delivered to Warehouse)
Q1 Stub/17
         
Dry Tonnes Milled 69,609   Copper (%) 26.4
      Gold (g/t) 13.6
Copper Recovery (%) 96.5      
Gold Recovery (%) 65.9   Dry Tonnes Produced 4,006
         
Copper Grade (%) 1.7   Saleable Copper Metal (t) 1,057
Gold Grade (g/t) 1.1   Saleable Gold (oz) 1,619
(see Note 1 below)

HIGHLIGHTS OF THE QUARTER:

  • Production of 4,006 tonnes of copper concentrate, representing a 2% decrease over Q4/16 resulting from a slightly lower copper head grade during the quarter.

  • Dry tonnes milled of 69,609 tonnes, equal to Q4/16 and a 20% increase over Q1/16, driven by an increase in production from the Lower Footwall Zone ('LFZ');

    • 1,057 tonnes of saleable copper
      (a 1% increase over Q4/16 and a 15% decrease over Q1/16)

    • 1,619 ounces of saleable gold
      (a 12% increase over Q4/16 and a 12% decrease over Q1/16)

  • Head grades of copper averaged 1.7% for the quarter (a 6% decrease over Q4/16); gold averaged 1.1 g/t (6% decrease over Q4/16). Grades for the 3 month period were in line with plan with the majority of LFZ ore now being sourced from either capital development or from the first post-pillar cut and fill ('PPCF') test stope outside of the known reserve. Once the LFZ is fully developed, ore will be primarily sourced from larger stopes. 

Click on, or paste the following link into your web browser, to view the associated PDF document.

http://www.rns-pdf.londonstockexchange.com/rns/6315Q_1-2016-11-30.pdf

This information is provided by RNS
The company news service from the London Stock Exchange

END



Contact

Contact:
RNS
Customer Services
0044-207797-4400
rns@londonstockexchange.com
http://www.rns.com


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Rambler Metals & Mining Plc
Bergbau
A0EQZZ
GB00B06Y3F14
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.