• Freitag, 15 November 2024
  • 05:22 Uhr Frankfurt
  • 04:22 Uhr London
  • 23:22 Uhr New York
  • 23:22 Uhr Toronto
  • 20:22 Uhr Vancouver
  • 15:22 Uhr Sydney

Gold Reach Resources Announces Positive Preliminary Economic Assessment for Ootsa Project

09.02.2016  |  CNW

Study supports potential to develop a low-cost copper-gold-molybdenum project

VANCOUVER, Feb. 9, 2016 /CNW/ - Gold Reach Resources (TSX-V; GRV) ("Gold Reach" or the "Company") is pleased to announce the summary results of an independent Preliminary Economic Assessment ("PEA") on the Company's 100% owned copper-gold-molybdenum Ootsa Project ("Ootsa Project") in west-central British Columbia. The conceptual study demonstrates the potential to develop the Ootsa Project by means of contract mining and toll milling at low initial capital cost to deliver a base case after-tax NPV and IRR of C$186 million and 81% respectively. P&E Mining Consultants Inc. ("P&E") was the lead engineering firm for the PEA, which also included input from Knight-Piesold Consulting, ERM Consultants Canada Ltd., and Gold Reach personnel.

"The Company is very encouraged with the outcome of the PEA," said Gold Reach President and CEO Dwayne Melrose.  "The results of the PEA support the concept that the Ootsa Project can be developed as a potential profitable, low-cost investment with an anticipated future upturn in metal prices."

BASE CASE OPERATING HIGHLIGHTS AND PROJECT PERFORMANCE:



·   Metal Price:                        

US$3.00/lb Cu, US$1260/oz Au, US$10.30/lb Mo, US$17/oz Ag



·   Mill Feed*:                           

65 Mt @ 0.37% Cu Eq (0.25% Cu, 0.13 g/t Au, 0.016% Mo, 2.3 g/t Ag)



·   Resource Quality:              

94% Measured, 6% Indicated Classification



·   Production:                         

324 M lbs Cu, 185 K oz Au, 15.8 M lbs Mo, 3 M oz Ag



·   Mine Life                             

12 years



·   Initial CAPEX:                      

C$64 million (including contingency)



·   NPV @ 5% (after-tax)**:      

C$186 million



·   IRR (after-tax):                    

81%



·   Payback:                              

1 year



·   Resilience:                          

31% IRR at US$2.25/lb Cu

*Consists of 61 M tonnes of the Measured portion of the mineral resource at grades of 0.25% Cu, 0.13 g/t Au, 0.016%Mo, and 2.3 g/t Ag, plus 4 M tonnes of the Indicated portion of the mineral resource at grades of 0.24% Cu, 0.07 g/t Au, 0.015%Mo, and 2.3 g/t Ag.

**NPV includes by-product credits for gold, molybdenum, and silver.  A discount rate of 5% was applied to generate NPV based on the lower risk of the development relative to that of similar projects.  A contingency factor of 30% was included in the initial capital cost estimate.

The PEA is based on the open pit development of the Ootsa Property by a contract miner, toll milling of Ootsa mill feed at the adjacent Huckleberry Mill at the end of current operations, and use of the existing site facilities on a fee-basis.  There are currently no agreements in place to conduct toll milling of Ootsa mill feed at the Huckleberry facilities, nor is there any guarantee that the required agreements can be established on commercially acceptable terms to support the proposed development plan. 

The projected mining method, potential production profile and other Ootsa Project economics referred to in this news release are summarized from a PEA, which will be filed on SEDAR within 45 days of this news release, and are conceptual in nature and additional technical studies will need to be completed in order to fully assess the Ootsa Project's viability. The PEA should not be considered a Pre-feasibility or Feasibility Study, as the economic and technical viability of the project have not been demonstrated to that level. There is no certainty that a potential mining operation will be realized or that a production decision will be made. A mine production decision that is made prior to completing a Feasibility Study carries potential risks that include, but are not limited to, the inclusion of Inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. Among other things, mine design and mining schedules, metallurgical flow sheets and process plant designs may require additional detailed work and economic analysis and internal studies to ensure satisfactory operational conditions and decisions regarding future targeted production. Capital cost estimates presented in this news release are preliminary in nature and will require a more detailed assessment in subsequent economic studies. Further, the advancement of the Ootsa Project is subject to requisite consents, permits and approvals, regulatory or otherwise for the Ootsa Project and there is no guarantee that Gold Reach would be successful in obtaining any or all of them.

"The key to developing a viable operating plan for the Ootsa Project was to fully recognize the nature of the value present in terms of the property; to use that value as the foundation for a plan that balanced investor risk and reward; and to take advantage of the unique circumstances offered by the proximity of an adjacent operating mine," continued Mr. Melrose.  "Gold Reach now looks forward to the challenge of refining the development concept for the Ootsa Project into an executable plan that builds on the results of the PEA." 

BASE CASE SUMMARY

ECONOMICS



NPV @ 5%

C$ M

186

IRR

%

81

Simple Payback

Yrs

1.0

Exchange Rate

US$:C$

0.80




UNIT COST



Direct Cash

US$/lb Cu

1.33

All-In Sustaining Cash   

US$/lb Cu

2.09




METAL PRICE



Cu

US$/lb

3.00

Au

US$/oz

1,260

Mo

US$/lb

10.30

Ag

US$/oz

17.00




INITIAL CAPITAL



Direct

C$ M

33

Indirect

C$ M

19

Contingency

C$ M

12

Total

C$ M

64




OPERATING COSTS



Mining

C$/t mined   

2.67

Processing

C$/t milled

10.07

G&A

C$/t milled

0.56




PRODUCTION



Cu

M lbs

324

Au

K oz

185

Mo

M lbs

15.8

Ag

M oz

3.0




MINING



Mill Feed

Mt

65

Waste

Mt

96

Total

Mt

161

Strip Ratio

w:o

1.46




HEAD GRADE



Cu

%

0.25

Au

g/t

0.13

Mo

%

0.016

Ag

g/t

2.3




PROCESS



Throughput

Mtpa

5.6

Mine life

Yrs

12




RECOVERY



Cu

%

91

Au

%

69

Mo

%

70

Ag

%

62

Operating Plan

The conceptual operating plan for the Ootsa Project is based on the sequential, open pit development of three deposits in close proximity to each other, by a mining contractor.  Crushed mill feed will be transported from Ootsa to the adjacent mill by means of an overland conveyor system employing a series of floating conveyor units to cross an intervening reservoir.  Preliminary metallurgical testwork indicates that the Ootsa feed could be processed at a rate of 5.6 Mtpa achieving copper recoveries of 90-92%.  Processing would be conducted on a toll-basis. 

Mineral Resources

An updated mineral resource model was developed utilizing a drill hole database comprised of 26,995 assays from 258 drill holes, including 7,311 m of drilling in 11 holes performed after the previous resource update.  Drill hole assay data was composited into 2 m intervals and a block model with 10 m by 10 m by 10 m block size was constructed using Gemcom modeling software.  Mineralized domains for all deposits were constrained incorporating geological, structural, and lithological parameters and using a $10/t NSR cut-off value.  Within these domains, a $8.50/t NSR cut-off value was applied to define the extent of mineralization with reasonable prospects for economic extraction.  Within these domains, grades for copper, gold, molybdenum, and silver were estimated using inverse distance squared (ID2) grade interpolation guided by geostatistical analysis.  The resulting resource model was subject to pit optimization using a Lerchs-Grossman algorithm to define a pit constrained mineral resource as detailed in the table below.

Ootsa Project Pit Constrained Mineral Resource Estimate at $8.50/t NSR Cut-off Value (1-5)

Deposit

Category

Tonnes
('000's)

CuEq
%

Cu
%

Au
g/t

Mo
%

Ag
g/t

CuEq
M lbs

Cu
M lbs

Au
K oz

Mo
M lbs

Ag
K oz

Ox

Measured

30,492

0.37

0.26

0.04

0.028

1.5

249

175

39

19

1,471

Indicated

3,204

0.32

0.23

0.04

0.021

1.4

23

16

4

1

144

M&I

33,696

0.37

0.26

0.04

0.027

1.5

272

191

43

20

1,615

East
Seel

Measured

22,165

0.43

0.28

0.26

0.002

2.5

210

137

185

1

1782

Indicated

1,422

0.38

0.28

0.14

0.003

4.4

12

9

6

0

201

M&I

23,587

0.43

0.28

0.26

0.002

2.6

222

146

191

1

1,983

West
Seel

Measured

134,491

0.37

0.21

0.16

0.022

3.2

1,097

623

692

65

13,837

Indicated

32,415

0.36

0.21

0.13

0.024

2.9

257

150

135

17

3,022

M&I

166,906

0.37

0.21

0.15

0.023

3.1

1,354

773

827

82

16,859

Inferred

5,212

0.30

0.18

0.09

0.019

2.6

34

21

15

2

436

Total

Measured

187,148

0.38

0.23

0.15

0.021

2.8

1,568

934

916

85

17,089

Indicated

37,041

0.35

0.21

0.12

0.023

2.8

286

175

146

19

3,368

M&I

224,189

0.37

0.22

0.15

0.021

2.8

1,854

1,109

1,062

104

20,457

Inferred

5,212

0.30

0.18

0.09

0.019

2.6

34

21

15

2

436

(1)

Mineral Resources, which are not mineral reserves, do not have demonstrated economic viability. The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues.



(2)

The quantity and grade of reported Inferred Resources in this estimation are uncertain in nature and there has been insufficient exploration to define these Inferred Resources as an Indicated or Measured Mineral Resource and it is uncertain if further exploration will result in upgrading them to an Indicated or Measured Mineral Resource category.



(3)

The Mineral Resources in this report were estimated using the Canadian Institute of Mining, Metallurgy and Petroleum (CIM), CIM Standards on Mineral Resources and Reserves, Definitions and Guidelines prepared by the CIM Standing Committee on Reserve Definitions and adopted by the CIM Council.



(4)

The $8.50/t NSR resource cut-off value grade was derived from Sep 30/15 three year approximate trailing average US metal prices of: Cu $3.25/lb, Au $1,350/oz, Mo $12/lb and Ag $22/oz and a US$:CDN$ exchange rate of 0.85. Process recoveries used were Cu 90%, Au 70%, Mo 70% and Ag 65% with respective smelter payables of 96%, 96%, 96% and 90%. Refining charges in US$ were Cu $0.05/lb, Au $5/oz and Ag $0.50/oz. C$ operating costs used were $2.25/t for mineralized material and waste mining, $1.50/t for overburden mining, $7.50/t for processing and $1.00/t for G&A. An optimized pit shell was utilized for resource reporting that utilized 45 degree slopes and an average mineralized material bulk density of 2.72 t/m3.



(5)

Copper Equivalent (Cu Eq) calculations are based on base case metal price and process recovery assumptions, and take into account smelter payable rates and refining costs. 

The updated mineral resource estimate for the Ootsa Project marks a large increase in resource confidence. Measured resources at the Ox deposit have increased from 11 Mt in the January 9, 2014 resource update to 31 Mt in the current update, an increase of 188%. The copper equivalent grade has also increased for the Measured category at Ox going from 0.34% Cu Eq (comprised of 0.21% Cu, 0.04 g/t Au, 0.029% Mo, and 1.6 g/t Ag) in the January 9, 2014 resource update to 0.37% Cu Eq (comprised of 0.26% Cu, 0.04 g/t Au, 0.028% Mo, and 1.5 g/t Ag) in the current estimate.  Measured resources at the East and West Seel deposits have increased from 28 Mt in the January 27, 2014 resource update to 157 Mt in the current update, an increase of 463%.  At the East Seel deposit the Cu Eq grade in the Measured category has increased slightly from 0.42% Cu Eq (0.25% Cu, 0.26 g/t Au, 1.5 g/t Ag) in the January 27, 2014 resource update to 0.43% Cu Eq (0.28% Cu, 0.26 g/t Au, 2.5 g/t Ag) in the current estimate.  At West Seel the Cu Eq grade in the Measured category has decreased slightly, from 0.40% Cu Eq (0.21% Cu, 0.15 g/t Au, 0.021% Mo, 3.8 g/t Ag) in the January 27, 2014 resource update to 0.37% Cu Eq (0.21% Cu, 0.16 g/t Au, 0.022% Mo, 3.2 g/t Ag) in the current resources estimate.

Mining

The conceptual mining plan uses conventional truck/shovel open pit methods employing an equipment fleet supplied and operated by a mining contractor.  Three pits will be mined sequentially over a period of 12 years including pre-stripping with mill feed conveyed to the nearby mill for processing.  Total mined tonnage will vary from 10-20 Mt annually depending on waste removal requirements. 

The mill feed is contained within an optimized subset of the mineral resource set out in the table above.  Collectively, the three pits contain 65 Mt of mill feed (inclusive of mining dilution and loss factors) averaging 0.37% Cu Eq (0.25% Cu, 0.13 g/t Au, 0.016% Mo, and 2.3 g/t Ag).  The mill feed is associated with 31 Mt of overburden and 65 Mt waste rock resulting in an overall life of mine strip ratio of 1.46:1.  It is notable that all mineral resources considered for mining are classified in the Measured and Indicated categories.

Milling

The nearby mill is expected to be able to process mill feed from the Ootsa Project without modification.  Material will be processed on a toll-basis at a rate of 5.6 Mtpa.  Metallurgical recoveries are based on preliminary testwork and vary by deposit as shown in the table below.

Mill feed will be supplied to the mill via a conveyor system owned by Gold Reach and operated by the mining contractor. 

Projected Metallurgical Recoveries


East Seel

West Seel

Ox

Cu

90%

92%

91%

Au

70%

65%

70%

Mo

---

70%

70%

Ag

60%

60%

65%

Infrastructure

The Ootsa Project lies on the south shore of the Nechako Reservoir, 6 km from the existing Huckleberry copper-molybdenum mine.  As such, road access, process plant, tailings storage, camp, and other support facilities already exist to support development.  Crushing, conveying, and field maintenance infrastructure will be established on the Ootsa side of the reservoir to support mining.  The added electrical load is estimated to be less than 2 MW and is expected to be supplied by the existing power line.

Access across the 1 km wide reservoir for equipment and personnel will be by a barge similar to the one that currently exists to facilitate logging operations on the Ootsa side of the reservoir.  Mill feed will be transferred from the mining areas to the mill via a conveyor system 9 km in length.  A series of floating conveyor units (similar to those often utilized by dredging contractors) integrated with the overland components will permit mill feed to move in a seamless, low-impact manner across the reservoir at a nominal average rate of 700 tph.

Capital Costs

The project development requires initial capital of C$64 M to construct the conveyor system, mobilize the contract mining fleet, prepare the first deposit for mining, and cover the cost of reclamation bonding.  An additional C$32 M in sustaining capital is required over the life-of-mine.  A contingency in the amount of 30% has been applied to all direct and indirect costs excluding pre-stripping.  A contingency has also been factored into the reclamation bond estimate separately.

Operating Costs

Unit operating costs used to determine Project value can be found in the table below.  Mining costs vary by material type and pit due to differences in haul distance, drill-blast cost, and the cost to transfer feed to the mill.  Processing costs vary from deposit to deposit based on differences in reagent consumption derived from testwork.  The total premium imposed on mining and milling costs for contract operation is approximately 30% and includes amortization, depreciation, administration, and margin. It is the opinion of P&E that the contract rates are consistent with industry norms and appropriate for the Ootsa Project.

Unit Operating Costs

Cost

Units

East Seel

West Seel

Ox

Contract Mining-Mill Feed

C$/t mined

2.95

3.02

2.90

Contract Mining-Overburden

C$/t mined

2.06

2.06

2.09

Contract Mining-Waste rock

C$/t mined

2.50

2.56

2.67

Toll Milling

C$/t milled

9.03

11.64

10.13

Owner G&A

C$/t milled

0.56

0.56

0.56

Environmental and Social

Total reclamation and closure costs are estimated at $9 M for the Ootsa Project including decommissioning and post-closure monitoring.  Preliminary testwork indicates that water from mining areas will meet discharge requirements without the need for complex treatment.  None of the proposed development is expected to directly alter any potential commercial, recreational, or Aboriginal fisheries within the reservoir.

Construction and mine development are expected to employ about 140 people during the 12 month pre-production period.  More significant, however, is that the development could secure longer term employment for the existing mine workforce and the benefits it brings to the local community for an additional 12 years.  First Nations bands in the area are supportive of responsible development and have engaged in positive dialogue with Gold Reach throughout the exploration phase of the Ootsa Project.

Project Schedule

As contemplated in the PEA, engineering, environmental studies, and permitting of the Ootsa Project are expected to take 3-4 years.  Construction would last 12 months during which infrastructure will be installed and the first pit pre-stripped.  Mining and processing would commence thereafter and continue for a period of 12 years.  At the end of operations, decommissioning would take 12-18 months followed by a minimum 5-year period of post-closure monitoring.

Economics

Financial performance is evaluated from the start of construction and does not consider the cost of permitting or financing.  The Ootsa Project has been evaluated using a 5% discount rate as, unlike many new mines, the development is premised on a tolling arrangement for the use of the adjacent Huckleberry assets, which obviates the risk associated with establishing access and constructing a mill and tailings facility.

Economics for the Ootsa Project are based on metal prices of US$3.00/lb Cu, $1,260/oz Au, $10.30/lb Mo, and $17.00/oz Ag, and at an exchange rate of C$1.00 = US$ 0.80.  Metal prices applied to the project represent a discount to prices projected for 2020 and beyond by various major financial institutions and forecasters.  This timing corresponds to when it is reasonably expected that the Ootsa Project could commence production.

Metal Price – Exchange Rate Sensitivity

Metal Price








Cu

US $/lb

2.25

2.50

2.75

3.00

3.25

3.50

Au

US $/oz

1,140

1,180

1,220

1,260

1,300

1,340

Ag

US $/oz

14.75

15.50

16.25

17.00

17.75

18.50

Mo

US $/lb

6.70

7.90

9.10

10.30

11.50

12.70

Forex

US$:C$

0.73

0.75

0.78

0.80

0.83

0.85









NPV @ 5% (after tax)

C$M

21

86

141

186

232

274

IRR (after tax)

%

31

54

69

81

92

103

Payback

yrs

1.6

1.2

1.1

1.0

0.9

0.8

The Ootsa Project has an estimated after-tax net present value (NPV) discounted at 5% of C$186 M, an internal rate of return (IRR) of 81%, and an undiscounted payback of 1 year.  The table above shows how the Ootsa Project value varies with changing metal prices and exchange rate.  The correlation between metal prices and exchange rate is a major contributor to the Ootsa Project's resilience at lower prices.

Direct and all-in sustaining cash costs are US$1.33/lb Cu and US$2.09/lb Cu respectively.  Direct cash costs refer to all on-site costs of production while all-in sustaining cash costs are all costs of production including sustaining capital.  All cash costs are calculated net of by-product credits.

Conclusions and Recommendations

P&E concludes that the Ootsa Project has economic potential as an open pit mining operation, utilizing the Huckleberry processing plant to produce copper and molybdenum concentrates. The PEA outlines 65 Mt of mill feed (inclusive of mining dilution and loss factors) averaging 0.37% Cu Eq (0.25% Cu, 0.13 g/t Au, 0.016% Mo, and 2.3 g/t Ag) within 3 pits.  The mill feed from the updated mineral resource estimate supporting this tonnage has a high level of confidence with 94% (61 Mt) occurring within the Measured category and 6% (4 Mt) occurring in the Indicated category with no Inferred resources in the mine plan.  The Ootsa Project has a low capital cost at C$64 million, a low strip ratio at 1.46:1, and robust economics with an after-tax NPV of C$186 million, an after tax IRR of 81%, and 1 year payback period using base case metal prices.

In the PEA, P&E recommends that Gold Reach advance the Ootsa Project with extended and advanced technical studies with the intention of moving the project toward a production decision.

QP Statement

The resource update and Preliminary Economic Assessment have been completed by P&E Mining Consultants Inc. in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects.  The updated mineral resource estimate has been prepared by Brian Ray, P.Geo. and Eugene Puritch, P.Eng., both Independent Qualified Persons as defined by National Instrument 43-101, and has an effective date of January 1, 2016.  The Preliminary Economic Assessment has been prepared under the supervision of Eugene Puritch, P.Eng, an Independent Qualified Person as defined by National Instrument 43-101, and has an effective date of January 1, 2016.  The PEA will be filed on SEDAR within 45 days of this news release.

Eugene Puritch, P.Eng., has reviewed and approved the technical disclosure in this news release for P&E Mining Consultants Inc.  Dr. Shane Ebert, Ph.D., P.Geo. is the Qualified Person for Gold Reach and has reviewed and approved the contents of this release.

ON BEHALF OF THE BOARD OF DIRECTORS

"Dwayne Melrose"
President & CEO

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Certain statements made and information contained in this news release and elsewhere constitutes "forward-looking information" within the meaning of Canadian securities legislation. Forward-looking statements are based on certain assumptions and are subject to risks and uncertainties which could cause actual events or results to differ from those reflected in the forward-looking statements, including, without limitation, with respect to statements regarding the PEA and updated resources estimate, the assumptions set forth in this news release (including the tolling arrangement terms for use of the Huckleberry assets), and risks and uncertainties relating to the interpretation of drill results and the estimation of mineral resources, the geology, grade and continuity of mineral deposits, the possibility that future exploration, development results will not be consistent with the Company's expectations, accidents, equipment breakdowns, risk of undiscovered, title defects and surface access, labour disputes, the potential for delays in exploration and permitting activities, the potential for unexpected costs and expenses, commodity price fluctuations, currency fluctuations, political risk and other risks and uncertainties, including those described under Risk Factors in each management discussion and analysis and in the Company's other disclosure which are available under the Company's profile at www.sedar.com.  Forward-looking information is based on various assumptions including, without limitation, the expectations and beliefs of management, the assumed long term price of copper, gold, silver and molybdenum, that the Company will receive required permits and access to surface rights, that the Company can access financing, appropriate equipment and sufficient labour and that the political environment within British Columbia will continue to support the development of environmentally safe mining projects. Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements. Accordingly, readers are advised not to place undue reliance on forward-looking statements.

This news release may use the terms "Measured", "Indicated", and "Inferred" as these terms are defined under Canada's National Instrument 43-101.  U.S. Investors are advised that, while such terms are recognized and required by Canadian regulations, they are not recognized by the United States Securities and Exchange Commission ("SEC") and may not be comparable to similar information for United States mining or exploration companies.  As such, certain information contained on this news release concerning descriptions of mineralization and resources under Canadian standards is not comparable to similar information made public by United States companies subject to the reporting and disclosure requirements of the SEC. U.S. investors are cautioned not to assume that any part or all of the mineral deposits described in these categories will ever be converted into proven or probable reserves, as defined in the SEC's Industry Guide No. 7.

SOURCE Gold Reach Resources Ltd.



Contact
Don Mosher, Telephone: 604-718-5454, Toll Free: 888-500-4587, Email: info@goldreachresources.com
Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Surge Copper Corp.
Bergbau
A2JENX
CA86881M1041
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.