• Samstag, 16 November 2024
  • 04:30 Uhr Frankfurt
  • 03:30 Uhr London
  • 22:30 Uhr New York
  • 22:30 Uhr Toronto
  • 19:30 Uhr Vancouver
  • 14:30 Uhr Sydney

Nevada Copper Files Integrated Feasability Study on SEDAR

10.07.2015  |  Marketwire

VANCOUVER, BRITISH COLUMBIA--(Marketwired - Jul 9, 2015) - Nevada Copper Corp. (TSX:NCU) ("Nevada Copper") (the "Company") is pleased to announce that it has completed, and SEDAR-filed, a National Instrument 43-101 ("NI 43-101") Integrated Feasibility Study Technical Report for its 100%-owned Pumpkin Hollow Copper Project located near Yerington, Nevada.

The Integrated Feasibility Study describes the proposed development of a 70,000 tons per day copper concentrator with mill feed from both open pit and underground mine operations. The Technical Report, entitled "NI 43-101 Technical Report Integrated Feasibility Study, Pumpkin Hollow Project Yerington, Nevada" ("IFS"), has an effective date of April 15, 2015. This technical report supersedes all previous technical reports on the Pumpkin Hollow Copper Project.

The IFS was prepared under the direction of Tetra Tech, Inc. ("Tetra Tech") with Stantec Consulting Services Inc. ("Stantec") having responsibility for the detailed underground mine design and underground capital cost estimation. Tetra Tech and Stantec are both industry-leading international engineering firms.

Highlights of the Integrated Feasibility Study (All dollar amounts are stated in United States currency)

Reserves and mine production are as reported in the May 28, 2015 press release however, certain costs differ slightly from previously reported amounts:

  • Long mine life of 23 years with low-risk profile located in an ideal mining jurisdiction close to existing infrastructure, an increase of 5 years from the first published integrated feasibility study, with production ramp-up targeted for 2018;
  • Assuming the Base Case of US$3.15 copper, US$1,200 gold and US$18 silver, the Integrated Project generates Life-of-Mine ("LOM") after-tax net cash flow of US$2.5 billion, NPV@ 5% of US$1.1 billion, an after-tax IRR of 15.6% with 4.7 year payback;
  • Significant LOM metal production of 4.5 billion pounds (2.05 million tonnes) of copper, 512,000 ounces of gold and 15.6 million ounces of silver in a quality copper concentrate. Average annual copper production of 275 million pounds in years 1 to 5;
  • The project development contemplates a 63,500 tons/day open pit mine and 6,500 tons/day underground mine, feeding a single 70,000 tons/day concentrator, generating substantial annual cash flow over LOM;
  • Proven and Probable Mineral Reserves, including open pit and underground mineable, are 572 million tons of ore grading 0.47% copper equivalent(1), containing 5.05 billion pounds of copper, 761,000 ounces of gold and 27.6 million ounces of silver;
  • Initial capital costs are estimated to be $1.04 billion including contingencies, excluding working capital of $33 million. Sustaining LOM capital is $0.63 billion;
  • Low LOM site operating costs of $11.80 per ton of ore-milled (Year 1 to 5 - C1 Production Costs at $1.49/lb. payable copper), excluding leased equipment and Nevada State Minerals Tax;
  • The IFS includes drilling data to 2011 for the underground deposits and 2013 for the open pit deposits. Further upside and optimization potential exists from current drilling in 2015 which is not included in the IFS; and
  • The IFS confirms the technical and financial viability of constructing and operating a 70,000 tons/day copper mining and processing operation at Pumpkin Hollow comprising a single large concentrator with mill feed from both open pit and underground operation.
(1) The copper grade equivalency was determined using Base Case metals prices and metallurgical recoveries of 89.3%, 67.3% and 56.3% for copper, gold and silver respectively

Annual copper production in concentrates and C1 operating costs:

Units Years 1-5* Years 1-10* LOM
(Average)
Copper in Concentrates 000s lbs./yr. 274,700 246,300 198,200
Copper in Concentrates Tonnes/yr. 124,600 111,700 89,900
C1 Production Costs** $/lb payable copper $1.49 $1.70 $1.76
* Note starting post ramp-up period
** The direct cash costs of mining, milling and concentrating, site administration and general expenses, concentrate treatment charges, and freight and marketing costs, less the net value of gold and silver by-product credits.

Summary of Economic Results:

Low Case Base Case High Case
Copper Price $/lb $2.85 $3.15 $3.75
Gold Price $/oz $1,200 $1,200 $1,200
Silver Price $/oz $18 $18 $18
(In Millions of US Dollars)
Net Smelter Revenue, after royalty $10,768 $11,990 $14,434
Net Cash Flow Pre-tax $1,831 $2,992 $5,315
Net Cash Flow After-tax $1,584 $2,514 $4,249
Annual Net Cash Flow Yr. 1-5 avg. $204 $262 $366
Pre-tax Operating Margin* Yr. 1-5 avg. $300 $380 $540
NPV 5% Pre-tax $659 $1,362 $2,768
NPV 5% After-tax $534 $1,100 $2,155
IRR Pre-tax 11.3 % 17.5 % 28.8 %
IRR After-tax 10.4 % 15.6 % 24.6 %
Payback - years Pre-tax 7.9 4.2 2.8
Payback - years After-tax 8.2 4.7 3.2
* Note: Net revenues less smelter charges, concentrate transport and site operating costs, including operating lease costs.

Capital Costs

The project initial capital costs are estimated at $1.04 billion with an accuracy of plus/minus 15% as of March 2015, including an initial contingency of $67 million. The contingency allowance is calculated based on assessed factors for each of the major Direct and Indirect cost categories.

The major direct cost items include development of the East underground mine, open pit mine equipment, leasing costs, North deposit pre-stripping, process plant, tailing storage facility, site infrastructure and offsite rail load-out facility. Indirect costs include such major areas as engineering and procurement, construction management, construction indirects, freight and commissioning, spares inventory, first fills, and Owners Costs.

Initial Sustaining Total
Area US$M US$M US$M
Open Pit Mine $263 $222 $485
Underground Mine 81 158 238
Ore Handling 12 2 15
Process Facility 268 52 320
Dry Stack Tailings Storage 69 79 148
Infrastructure 88 0 88
Water Management 18 2 19
Environmental & Reclamation 12 41 54
Subtotal Directs 811 556 1,367
Construction Indirects 66 35 101
Spares & Warehouse Inventory 10 2 12
Initial Fills 4 0 4
Freight & Logistics 15 2 17
Commissioning & Start-Up 2 0 2
EPCM 58 0 58
Vendor & Consulting Assistance 1 0 1
Subtotal In-directs 156 39 195
Contingency 67 39 106
Owner Costs 7 0 7
Total Capital $1,041 $634 $1,675
Note: totals may not add due to rounding

Working capital required for initial operations is estimated to be $33 million.

LOM sustaining capital totals $0.63 billion and includes development costs associated with the E2 underground deposit and related equipment; South open pit deposit development costs; replacement of, and additions to, surface mobile equipment; expenditures on the tailings storage facility, and reclamation costs, net of salvage value at the conclusion of the project.

Operating Costs

LOM site unit operating cash costs, net of capitalized pre-stripping and other predevelopment costs, are $11.80 per ton-milled, as summarized in the table below:

LOM Unit Operating Cost Summary
Area $/ton-milled
Open Pit Mining $5.03
Underground Mining 1.45
Processing 4.73
Tailings & Water Management 0.17
Environmental 0.02
G&A 0.40
Total LOM Site Operating Costs $11.80
Note: The cost of operating leases and Nevada Net Proceeds of Mining tax adds $0.72/ton and $0.28/ton, respectively.

Unit open pit mining cash costs average $5.34 per ton of open pit ore mined and milled. This equates to $1.16 per ton of open pit material mined, including waste and ore. Average LOM strip ratio for the North and South deposits is 3.59. Underground mining costs average $24.06 per ton of underground ore mined, excluding $1.25 for truck transport of ore to concentrator.

LOM Unit Mining Costs
Open Pit Underground
($/ton of open pit ore mined) ($/ton of underground ore mined)
$5.34/ton $24.06/ton

A power cost of $0.065/kwh was used for IFS purposes, based on NV Energy expected rates.

Qualified Persons

In November 2014 Nevada Copper commissioned Tetra Tech and Stantec to prepare an updated Pumpkin Hollow Project Integrated Feasibility Study Technical Report in accordance with NI 43-101. The scientific and technical information in this release has been reviewed and approved by Mr. Ed Lips, PE, of Tetra Tech, who is overall manager for the IFS and who is an Independent Qualified Person within the meaning of NI 43-101. It has also been reviewed by Mr. Mel Lawson, SME-RM, Principal/Senior Consulting Engineer, Stantec Consulting Services Inc. who is an Independent Qualified Person within the meaning of NI 43-101.

This release was also reviewed by Gregory French, P.G., Vice-President Exploration & Project Development of Nevada Copper, Timothy D. Arnold, PE, Vice President of Operations and Robert McKnight, P. Eng., Executive Vice-President of Nevada Copper, all of whom are Non-independent Qualified Persons within the meaning of NI 43-101.

Readers should refer to the IFS for further details of the project development. The IFS will be filed in accordance with NI 43-101 on SEDAR (www.sedar.com).

NEVADA COPPER CORP.

Giulio T. Bonifacio, President & CEO

We seek safe harbour.



Contact

Nevada Copper Corp.
Eugene Toffolo
Corporate Communications
604-683-8266 or Toll free: 1-877-648-8266
etoffolo@nevadacopper.com
Nevada Copper Corp.
Robert McKnight, P.Eng.
Executive Vice President
604-683-1309
bmcknight@nevadacopper.com


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Nevada Copper Corp.
Bergbau
-
-
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.