• Freitag, 15 November 2024
  • 05:24 Uhr Frankfurt
  • 04:24 Uhr London
  • 23:24 Uhr New York
  • 23:24 Uhr Toronto
  • 20:24 Uhr Vancouver
  • 15:24 Uhr Sydney

Tiger Resources Limited Achieves Commercial Production at Kipoi

13.08.2014  |  ABN Newswire
Perth, Australia (ABN Newswire) - Tiger Resources Ltd. (ASX:TGS) is pleased to announce that the solvent-extraction and electro-winning (SXEW) plant at its Kipoi Copper Project in the Democratic Republic of Congo (DRC) has achieved commercial production of copper cathode.

The Company achieved the milestone of commercial production during July, producing 1,501 tonnes of copper cathode operating at 72% of nameplate design.

Tiger's Managing Director Brad Marwood said the achievement of commercial production within six weeks of start-up demonstrated the quality of the project and on-site team.

"We have a very good operating team and we are vigorously pursuing the next target of full design capacity of 2,083t per month of copper cathode," Mr Marwood added.

"It can often take more than six months to bring an SXEW plant to full production; I expect we will beat this target."

Tiger expects the plant to produce 14,000 tonnes of copper cathode this calendar year, and 25,000 tonnes of cathode in its first full 12 months of commercial production.


BACKGROUND

The Kipoi Copper Project is located approximately 75km NNW of Lubumbashi in the Katanga Province of the DRC. Tiger has a 60% interest in La Société d'Exploitation de Kipoi SPRL (SEK), a DRC-registered company which holds the project assets and is the operator at Kipoi.

Tiger undertook a phased development at Kipoi. Its Stage 2 solvent extraction electro-winning (SXEW) plant commenced production of copper cathode in May 2014. This first phase of the SXEW plant is expected to produce 25,000 tonnes of copper cathode in its first 12 months of commercial production. The Stage 1 heavy media separation (HMS) plant has been in production at Kipoi since 2011.

Stage 1 HMS operations have produced stockpiles with 159,600 tonnes of contained copper. These stockpiles are providing feed for the SXEW plant for the first three years of its operation.

The forecasted SXEW life of mine (LOM) site cash operating cost is $1.04/lb, and forecast LOM C3 cost (all-in cost, including capital expenditure) is US$1.75/lb.

It is envisaged that ore from Judeira and other deposits within the Kipoi Project area, and within the nearby 100%-owned Lupoto Project, will also be processed during the SXEW operations, providing additional returns and increasing the ore reserves available as feedstock to the SXEW plant. Increased resources from these deposits will potentially increase the mine life and/or the annual plant throughput.


About Tiger Resources Limited:

Tiger Resources Ltd. (ASX:TGS) has established itself as a producing copper/cobalt company with excellent growth potential after making the transition from an explorer. We have a highly-rated portfolio of properties, all strategically located on the world renowned Katanga Copperbelt in the Democratic Republic of the Congo (DRC), central Africa.



Contact:

Tiger Resources Ltd.
Brad Marwood, Managing Director
Tel: (+61 8) 6188 2000
Email: bmarwood@tigerez.com

Stephen Hills, Finance Director
Tel: (+61 8) 6188 2000
Email: shills@tigerez.com

Nathan Ryan, Investor Relations
Tel: (+61 0)420 582 887
Email: nryan@tigerez.com
Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Tiger Resources Ltd.
Bergbau
A0CAJF
AU000000TGS2
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.