Banks Island Gold Ltd. Reports Update on Underground Mining at Yellow Giant
VANCOUVER, BRITISH COLUMBIA--(Marketwired - Jul 17, 2014) - Banks Island Gold Ltd. (TSX VENTURE:BOZ) -
- Mine development for initial production mining at Tel Zone near completion.
- 11,000 tonnes of mineralized material currently in surface stockpile.
- Production mining of 25,000 tonnes at Tel Zone to commence on July 30th.
- 6 months of mill feed available (36,000t) at start of flotation concentrate production in early August.
Banks Island Gold Ltd. (the "Company") is pleased to report an update on progress at the Yellow Giant Gold Property ("Yellow Giant"), located on Banks Island, British Columbia.
At present the Company has 11,000 tonnes of broken mill feed stockpiled and will have a 25,000 tonne stope ready for production mining at the Tel Zone by July 30th 2014. At a production rate of 200 tonnes per day, the Company has approximately 6 months of mineralized material available for processing once the grinding and flotation circuits are commissioned and ready for production in early August.
The Company plans to continue mine development at the Tel Zone and other zones at Yellow Giant in order to maintain a healthy inventory of material available for processing.
Bob Zone
The Company estimates that approx. 2,000 tonnes of mineralized material remains in broken inventory at the Bob Zone which will be processed once the grinding and flotation sections are commissioned. The arithmetic average of assays of mill feed from the Bob Zone to date is 21.0gpt Au and 51gpt Ag.
The Company plans to backfill the upper Bob Zone stope with cemented tailings, complete a service/ventilation raise from the lower workings to surface, and then continue underground development to access planned mining stopes below the B30 level.
Tel Zone
As of July 15th 2014, underground mine development crews had completed 445m of tunneling at the Tel Zone, including 375m of waste development and 70m of ore development.
Waste development to the third level at the Tel Zone is estimate to be complete on July 30th. Completion of the third level development will allow mining of a 25,000 tonne block of the mineral resource. This production area, the Upper Tel Zone, represents approximately 57% of the total mineral resource at the Tel Zone.
Mining of mineralization at the Tel Zone will commence in August 2014 and coincide with the start of production of flotation concentrates. Mine development of the main ramp will continue concurrently with production mining in order to access planned mining stopes below the third level.
The current Mineral Resource for the Tel Zone is displayed in Table 1 and is effective as of February 1st 2013. The mineral resource is stated at a 6gpt Au cut-off grade.
Table 1 - Current Mineral Resource - Tel Zone | |||||||||
Zone | Measured | Indicated | Inferred | ||||||
Tonnes | Au Grade | Ag Grade | Tonnes | Au Grade | Ag Grade | Tonnes | Au Grade | Ag Grade | |
(gpt) | (gpt) | (gpt) | (gpt) | (gpt) | (gpt) | ||||
Tel | 15,000 | 21.1 | 43 | 21,000 | 18.5 | 41 | 8,000 | 20.6 | 40 |
Total Measured & Indicated: | 36,000 tonnes @ 19.6gpt Au & 42gpt Ag | = 22,700oz Gold, | 48,000oz Silver |
Total Inferred: | 8,000 tonnes @ 20.6gpt Au & 40gpt Ag | = 5,300oz Gold, | 10,000oz Silver |
The NI43-101 Technical Report on the Yellow Giant Gold Property dated February 1st 2013 was prepared by independent consultant, Mr. Robert Baldwin, P.Eng, has been posted on SEDAR and will be available on the Company's website.
Stockpile
As reported by news release on July 10th 2014, the Company estimates there are currently 6,000 tonnes of DMS fines stockpiled onsite which are composed of material rejected by the Spiral Concentrator.
The Company has sampled material from its DMS fines stockpiles. The average of 14 samples ranged from 7.8gpt Au to 62.9gpt Au with an arithmetic average of 19.9gpt Au and 51gpt Ag.
The Company also has a stockpile of mineralized material mined recently from the Tel Zone with an estimated quantity of 3,000 tonnes. Assays from mined material at Tel are pending.
To view Figure 1, click on the following link: http://media3.marketwire.com/docs/BOZ717.jpg
Mr. Benjamin Mossman, P.Eng, CEO of Banks Island Gold, is the qualified person who reviewed and approved the contents of this news release.
Analytical work on concentrates was carried out by ALS Mineral Services in North Vancouver, British Columbia. Quality assurance and quality control programs include the use of analytical blanks, standards, and duplicates in addition to the lab's own internal quality assurance program. Samples are fire assayed with a gravimetric finish to determine gold and silver values.
The Company is a mining company focused on gold production, exploration, and development of economically viable mineral resources. The Company's mineral property is located in British Columbia. For more information, please refer to the Company's website at www.banksislandgold.com
ON BEHALF OF THE BOARD OF DIRECTORS
Benjamin W. Mossman, P.Eng, President, Director, & Chief Executive Officer
The TSX Venture Exchange has not reviewed and does not accept responsibility for the accuracy or adequacy of this release. Neither the TSX Venture Exchange nor its Regulation Service Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
This press release contains forward-looking statements. All statements, other than statements of historical fact, constitute "forward-looking statements" and include any information that addresses activities, events or developments that the Company believes, expects or anticipates will or may occur in the future including the Company's strategy, plans or future financial or operating performance and other statements that express management's expectations or estimates of future performance.
Forward-looking statements are generally identifiable by the use of the words "may", "will", "should", "continue", "expect", "anticipate", "estimate", "believe", "intend", "plan" or "project" or the negative of these words or other variations on these words or comparable terminology. These statements, however, are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of the Company to be materially different from those expressed, implied by or projected in the forward-looking information or statements. Important factors that could cause actual results to differ from these forward-looking statements include but are not limited to: risks related to the exploration and potential development of the Company's project, the actual results of current exploration activities, conclusions of economic evaluations, changes in project parameters as plans continue to be refined, future prices of gold, as well as those factors discussed in the sections relating to risk factors of the Company Annual Information Form dated February 22, 2013 filed on SEDAR.
There can be no assurance that any forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, the reader should not place any undue reliance on forward-looking information or statements. Except as required by law, the Company does not intend to revise or update these forward-looking statements after the date of this document or to revise them to reflect the occurrence of future unanticipated events.